Permit Details

Status:
In Revision
Type:
Commercial Building
Address NEW:
3350 E VALENCIA RD
Apply Date:
11/12/2024
Applicant:
Ian Regan
Description:
Open Lab Area (Warehouse)

Permit Reviews

Permit Number - TC-COM-1124-02168
Permit Status: In revision
Permit Description: Open Lab Area (Warehouse)
Start Date Submittal Complete Date Status  
02/11/2025 RESTAMP - COMMERCIAL v.1 02/13/2025 APPROVED Review Details
01/13/2025 COMMERCIAL REVIEW - FULL v.2 02/04/2025 REQUIRES RESUBMIT Review Details
04/02/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 04/07/2025 APPROVED Review Details
02/20/2026 COMMERCIAL REVIEW - FULL REVISION v.1 N/A IN REVIEW Review Details
02/11/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/12/2026 REQUIRES RESUBMIT Review Details
03/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/02/2025 REQUIRES RESUBMIT Review Details
02/08/2025 COMMERCIAL REVIEW - FULL v.3 02/08/2025 REQUIRES RESUBMIT Review Details
11/13/2024 COMMERCIAL REVIEW - FULL v.1 12/10/2024 REQUIRES RESUBMIT Review Details
12/19/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/22/2025 REQUIRES RESUBMIT Review Details
02/10/2025 COMMERCIAL REVIEW - FULL v.4 02/11/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-1124-02168
Permit Status: In revision
Permit Description: Open Lab Area (Warehouse)
Total Outstanding Activity Conditions - 6
Date Name
02/11/2025 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
02/11/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/11/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/11/2025 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
02/11/2025 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
02/11/2025 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-1124-02168
Permit Status: In revision
Permit Description: Open Lab Area (Warehouse)
Date Description Comments
11/13/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
02/08/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
02/11/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: In Revision
Permit Number: TC-COM-1124-02168
Permite Description: Open Lab Area (Warehouse)
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
02/04/2026 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass 2-4-26: partial pass on exterior clips/sheathing-pending revision approval. Okay to continue with construction at own risk but do not cover anything.
01/20/2026 COT - HCBU - Framing N/A Not Ready 1/20/2026 provide city approved plans prior to inspection.
02/04/2026 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 2-4-26: exterior receptacles require bubble cover or covers that rated "heavy duty " while in use. Exterior lighting heights meet code requirements and verified supports on conduits for above ceiling lights/and in wall exterior receptacles. Okay to continue with construction at progress areas.
10/28/2025 COT - HCEL - Electrical Progress N/A Partial Pass
02/17/2026 COT - HCPL - Plumbing Intermediate N/A Partial Pass 2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas.
10/02/2025 COT - HCPL - Plumbing Progress N/A Partial Pass 10-2-25: referred contractor to engineering department supervisor for storm drain questions/inspections.
02/17/2026 COT - HCME - Mechanical Intermediate N/A Partial Pass 2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas.
02/17/2026 COT - HCME - Mechanical Progress N/A Partial Pass 2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas.
02/17/2026 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas.
02/17/2026 COT - HCME - Mechanical Above Ceiling N/A Partial Pass 2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-42201.00 AHJ RESPONSE COMPOSITE DRAWINGS_V3.PDF DOCUMENTS VIEW
122421 FREEPORT TUCSON 42201.00 STRUCTURAL CALCULATIONS_V2.PDF DOCUMENTS VIEW
22-125 FREEPORT TECHNOLOGY CENTER GEOTECHNICAL REPORT_V2.PDF DOCUMENTS VIEW
COMCHECK-42201.00 FMI-TCT TUCSON-SIGNED_V2.PDF DOCUMENTS VIEW
TRANE TRACE OUTPUTS 25-0206_V2.PDF DOCUMENTS VIEW