Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 02/17/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
2-17-26: Reno (copper) piping verified per mechanical & details. System verified under test at 150 psi.-okay to continue with construction at progress areas. |
| 10/01/2025 |
COT - HCPL - Plumbing Progress |
|
Re-inspection required |
10-1-25: called point of contact 3 different . Last attempt was at 1114-Verizon answering message indicated that party was unavailable. Left site at 1124-reschedule when available. |
| 10/02/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
10-2-25: referred contractor to engineering department supervisor for storm drain questions/inspections. |