Description:
The scope of this project consists of the following: 1. New CT, Control Room, Supply, and Equipment will occupy 838 SF of the existing shell space. 2. The total remodeled area of existing Corridor is 234 SF. 3. The total remodeled area of existing Control Room is 142 SF. 4. The ADD ALT Patient Hold will occupy 327 SF of existing shell space. 5. The new CT to be comprised of the following: a. (1) Class 1 CT and its associated support spaces. b. (1) Shared Control Room with existing CT. c. (1) Equipment Room for New CT. d. (1) Clean Supply e. (1) Equipment Room with (6) lockers. f. (1) Equipment Alcove. g. (1) CT Sub Waiting Alcove.

Permit Reviews

Permit Number - TC-COM-1124-02102
Permit Status: Inspections complete
Permit Description: The scope of this project consists of the following: 1. New CT, Control Room, Supply, and Equipment will occupy 838 SF of the existing shell space. 2. The total remodeled area of existing Corridor is 234 SF. 3. The total remodeled area of existing Control Room is 142 SF. 4. The ADD ALT Patient Hold will occupy 327 SF of existing shell space. 5. The new CT to be comprised of the following: a. (1) Class 1 CT and its associated support spaces. b. (1) Shared Control Room with existing CT. c. (1) Equipment Room for New CT. d. (1) Clean Supply e. (1) Equipment Room with (6) lockers. f. (1) Equipment Alcove. g. (1) CT Sub Waiting Alcove.
Start Date Submittal Complete Date Status  
12/20/2024 RESTAMP - COMMERCIAL v.1 12/24/2024 APPROVED Review Details
04/09/2026 SPECIAL INSPECTION REVIEW v.3 04/10/2026 APPROVED Review Details
03/11/2026 SPECIAL INSPECTION REVIEW v.2 03/12/2026 REQUIRES RESUBMIT Review Details
12/18/2024 COMMERCIAL REVIEW - FULL v.2 12/20/2024 APPROVED Review Details
11/01/2024 COMMERCIAL REVIEW - FULL v.1 11/27/2024 REQUIRES RESUBMIT Review Details
04/10/2026 COMMERCIAL REVIEW - FULL REVISION v.1 05/04/2026 APPROVED Review Details
02/23/2026 SPECIAL INSPECTION REVIEW v.1 02/23/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1124-02102
Permit Status: Inspections complete
Permit Description: The scope of this project consists of the following: 1. New CT, Control Room, Supply, and Equipment will occupy 838 SF of the existing shell space. 2. The total remodeled area of existing Corridor is 234 SF. 3. The total remodeled area of existing Control Room is 142 SF. 4. The ADD ALT Patient Hold will occupy 327 SF of existing shell space. 5. The new CT to be comprised of the following: a. (1) Class 1 CT and its associated support spaces. b. (1) Shared Control Room with existing CT. c. (1) Equipment Room for New CT. d. (1) Clean Supply e. (1) Equipment Room with (6) lockers. f. (1) Equipment Alcove. g. (1) CT Sub Waiting Alcove.
Date Description Comments
12/19/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
12/24/2024 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
11/01/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
12/19/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/19/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
12/19/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
12/18/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
12/19/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
12/19/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-1124-02102
Permite Description: The scope of this project consists of the following: 1. New CT, Control Room, Supply, and Equipment will occupy 838 SF of the existing shell space. 2. The total remodeled area of existing Corridor is 234 SF. 3. The total remodeled area of existing Control Room is 142 SF. 4. The ADD ALT Patient Hold will occupy 327 SF of existing shell space. 5. The new CT to be comprised of the following: a. (1) Class 1 CT and its associated support spaces. b. (1) Shared Control Room with existing CT. c. (1) Equipment Room for New CT. d. (1) Clean Supply e. (1) Equipment Room with (6) lockers. f. (1) Equipment Alcove. g. (1) CT Sub Waiting Alcove.
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
05/30/2025 COT - HCEL - Electrical Intermediate N/A Partial Pass In wall electric in rooms 11650, 11651B, 11562, 11654. Ok to insulate and Sheetrock progress areas.
10/29/2025 ENGR Engineering Final N/A Partial Pass 10/29/25 - Public access is good. Phase 4 is good.
10/30/2025 COT - FCON - Sprinkler - Final N/A Partial Pass phase 4 complet
10/29/2025 COT - HCBU - Building Final N/A Partial Pass Phase 4 is complete: OK to occupy,completed area.
06/06/2025 COT - HCEL - Electrical Above Ceiling N/A Partial Pass In wall electric for work stations on South side of x-ray room. In addition, this inspection includes exterior walls of x-ray room (North, South, West); sheet rock nailing. Ok yo,tape progress areas.
05/23/2025 COT - HCPL - Plumbing Progress N/A Partial Pass
10/28/2025 COT - HCBU - Building Above Ceiling N/A Partial Pass 10-28-25: phase 4 ER Room, verified drywall layer of 5/8" properly sealed on smoke wall. Okay to continue with construction at progress areas.
05/30/2025 COT - HCBU - Framing N/A Partial Pass Rooms 11650, 11651B, 11652, 11654. Ok to insulate and sheet rock progress areas.
10/30/2025 COT - FCON - Alarm - Final N/A Partial Pass Phase 4 passed.
04/21/2026 BULD - Electrical Clearance N/A Not Applicable
04/21/2026 COT - BULD - SWG Clearance N/A Not Applicable
04/21/2026 COT - HCBU - Exterior Clips/Sheathing N/A Not Applicable
04/21/2026 COT - HCME - Mechanical Progress N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-1124-02102
Permit Description: The scope of this project consists of the following: 1. New CT, Control Room, Supply, and Equipment will occupy 838 SF of the existing shell space. 2. The total remodeled area of existing Corridor is 234 SF. 3. The total remodeled area of existing Control Room is 142 SF. 4. The ADD ALT Patient Hold will occupy 327 SF of existing shell space. 5. The new CT to be comprised of the following: a. (1) Class 1 CT and its associated support spaces. b. (1) Shared Control Room with existing CT. c. (1) Equipment Room for New CT. d. (1) Clean Supply e. (1) Equipment Room with (6) lockers. f. (1) Equipment Alcove. g. (1) CT Sub Waiting Alcove.
Total Completed Inspections - 21
Date Description Inspector Results Comments
03/19/2025 COT - HCEL - Electrical Progress Passed CT and ED expansion.
01/06/2026 ENGR Engineering Final Passed
01/06/2026 COT - FCON - Sprinkler - Final Passed
01/06/2026 COT - FCON - Fire - Final Passed
01/09/2026 COT - HCBU - Building Final Passed
01/16/2026 COT - HCEL - Electrical Above Ceiling Passed
01/16/2026 COT - HCPL - Plumbing Progress Passed
01/16/2026 COT - HCBU - Building Above Ceiling Passed
01/16/2026 COT - HCBU - Framing Passed
01/16/2026 COT - FCON - Alarm - Final Passed
04/21/2026 TRSP - ROW - Final/Close-Out Passed all work completed in the building work in the right of way
04/21/2026 COT - HCBU - Building Progress Passed
04/21/2026 COT - HCBU - Preslab Passed
04/21/2026 COT - HCEL - Electrical Final Passed
04/21/2026 COT - HCME - Mechanical Above Ceiling Passed
04/21/2026 COT - HCME - Mechanical Final Passed
04/21/2026 COT - HCME - Mechanical Intermediate Passed
04/21/2026 COT - HCPL - Plumbing Above Ceiling Passed
04/21/2026 COT - HCPL - Plumbing Final Passed
05/11/2026 COT - HCBU - CofO Passed
05/11/2026 COT - HCPL - Plumbing Intermediate Passed

Documents

File Name Document Type  
BUMCT ED CT ADDITION_ NARRATIVE_CITY RESUBMITTAL_20260306_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI CONCRETE COMPRESSIVE STRENGTH TEST REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI CONCRETE SAMPLING REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI FIELD DENSITY REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI FIREPROOFING OBSERVATION REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI MEDICAL GAS INVOICES_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI POST-INSTALLED ANCHORS REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI REINFORCING STEEL OBSERVATIONS REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI REPORT MEDICAL GAS CERTIFICATE_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI REPORT POINTS OF CONTACT_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_SSI WELDING OBSERVATION REPORTS_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_TC-COM-1124-02102_SPECIAL INSPECTION CERTIFICATE_REPORTS-2026-03-06_V2.PDF DOCUMENTS VIEW
BUMCT CT ADDITION_TC-COM-1124-02102_SPECIAL INSPECTION MED GAS CERTIFICATE_REPORTS_V2.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-BUMCT NEW CT - COMBINED SET - CITY COMMENTS 1 - 20241212_V2.PDF DOCUMENTS VIEW
29-224159-0 GEOTECH LETTER, 2925JH049_V1.PDF DOCUMENTS VIEW
BUMCT CT ADDITION - SUPPLIMENTAL STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
BUMCT ED CT - REVISION NARRATIVE - 20241212_V1.PDF DOCUMENTS VIEW