Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-1123-02713
Permit Details
Apply Date:
11/22/2023
Applicant:
Dick Stover
Description:
construction documents for a 1489 sf expansion of a 3468 sf existing medical office in an existing building
Permit Reviews
Permit Number - TC-COM-1123-02713
Permit Status: Complete
Permit Description: construction documents for a 1489 sf expansion of a 3468 sf existing medical office in an existing building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/28/2024 | APPROVED |
11/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/20/2023 | APPROVED |
Conditions
Permit Number - TC-COM-1123-02713
Permit Status: Complete
Permit Description: construction documents for a 1489 sf expansion of a 3468 sf existing medical office in an existing building
Date | Description | Comments |
---|---|---|
11/30/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
11/22/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
11/30/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02713
Permite Description: construction documents for a 1489 sf expansion of a 3468 sf existing medical office in an existing building
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/15/2024 | COT - HCPL - Sewer | N/A | Not Applicable | |
05/24/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | Not required. No natural gas to suite. |
05/24/2024 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Sprinkler head in the back of the reception area needs to be moved it is blocked by the cabinets. |
05/24/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Sprinkler head in the back of the reception area needs to be moved it is blocked by the cabinets. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02713
Permit Description: construction documents for a 1489 sf expansion of a 3468 sf existing medical office in an existing building
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/15/2024 | COT - HCBU - Framing | Passed | ||
02/15/2024 | COT - HCEL - Electrical Progress | Passed | ||
02/15/2024 | COT - HCPL - Plumbing Progress | Passed | ||
04/02/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
04/02/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
04/11/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/11/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
05/03/2024 | COT - FCON - Alarm - Final | Passed | ||
05/03/2024 | ENGR Engineering Final | Passed | ||
05/03/2024 | COT - HCBU - Building Final | Passed | ||
05/03/2024 | COT - HCBU - Building Progress | Passed | ||
05/03/2024 | COT - HCEL - Electrical Final | Passed | ||
05/03/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
05/03/2024 | COT - HCME - Mechanical Final | Passed | ||
05/03/2024 | COT - HCME - Mechanical Progress | Passed | ||
05/03/2024 | COT - HCME - Venting | Passed | ||
05/03/2024 | COT - HCPL - Plumbing Final | Passed | ||
05/24/2024 | BULD - Electrical Clearance | Passed | 5/24/24: Dryer box has been added, solder connections have been corrected. Okay to proceed with installation of insulation and drywall. | |
05/24/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
05/24/2024 | COT - HCBU - CofO | Passed | Remodeling project is complete and tenant has moved into suite. Okay to issue Certificate of Completion or Occupancy for this permit. | |
06/05/2024 | COT - FCON - Sprinkler - Final | Passed | ||
06/05/2024 | COT - FCON - Fire - Final | Passed |