Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
11/21/2023
Applicant:
Marni Allen
Description:
-We will dig up approx. 15' from the meter in the backyard of unit #1 to the back (exterior) wall of the building. We will install new 1" P.P pipe with tracer wire and steel risers. We will install new 1/4 turn isolation valve at the building. We will then run steel pipe up to the roof. We will run new 1" steel pipe approx. 70". We will install tee to supply the furnace and then run 3/4" pipe to the furnace and down the exterior wall for the water heater. We will install new 1/4 turn gas valve and gas flex supply lines for the water and the furnace. Also install sediment taps on the water heater and furnace. We will install bonding wire between the gas pipe and the cold-water lin. We will install carbon monoxide detector in the home. WE will place gas line on 15psi pressure test and schedule inspection. After inspection we will back fill trench. Re-pipe is for Unit #4.

Permit Reviews

Permit Number - TC-COM-1123-02702
Permit Status: Issued
Permit Description: -We will dig up approx. 15' from the meter in the backyard of unit #1 to the back (exterior) wall of the building. We will install new 1" P.P pipe with tracer wire and steel risers. We will install new 1/4 turn isolation valve at the building. We will then run steel pipe up to the roof. We will run new 1" steel pipe approx. 70". We will install tee to supply the furnace and then run 3/4" pipe to the furnace and down the exterior wall for the water heater. We will install new 1/4 turn gas valve and gas flex supply lines for the water and the furnace. Also install sediment taps on the water heater and furnace. We will install bonding wire between the gas pipe and the cold-water lin. We will install carbon monoxide detector in the home. WE will place gas line on 15psi pressure test and schedule inspection. After inspection we will back fill trench. Re-pipe is for Unit #4.
Start Date Submittal Complete Date Status  
11/21/2023 COMMERCIAL PDSD SIMPLE REVIEW v.1 11/22/2023 APPROVED Review Details

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-1123-02702
Permit Description: -We will dig up approx. 15' from the meter in the backyard of unit #1 to the back (exterior) wall of the building. We will install new 1" P.P pipe with tracer wire and steel risers. We will install new 1/4 turn isolation valve at the building. We will then run steel pipe up to the roof. We will run new 1" steel pipe approx. 70". We will install tee to supply the furnace and then run 3/4" pipe to the furnace and down the exterior wall for the water heater. We will install new 1/4 turn gas valve and gas flex supply lines for the water and the furnace. Also install sediment taps on the water heater and furnace. We will install bonding wire between the gas pipe and the cold-water lin. We will install carbon monoxide detector in the home. WE will place gas line on 15psi pressure test and schedule inspection. After inspection we will back fill trench. Re-pipe is for Unit #4.
Total Completed Inspections - 2
Date Description Inspector Results Comments
12/14/2023 COT - LCPL - Gas Pressure Test Passed
12/14/2023 COT - LCPL - Plumbing Final Passed No clearance at this time; vacant unit.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
315 E BLACKLIDGE UNIT 4_V1.PDF DOCUMENTS VIEW