Permit: TC-COM-1122-00154
Permit Details
Apply Date:
11/21/2022
Applicant:
Lisa Bowers
Description:
New Commercial Shell building
Permit Reviews
Permit Number - TC-COM-1122-00154
Permit Status: Complete
Permit Description: New Commercial Shell building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/19/2023 | APPROVED |
03/02/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/23/2023 | REQUIRES RESUBMIT |
10/23/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/01/2023 | APPROVED |
04/07/2023 | RESTAMP - COMMERCIAL v.1 | 04/10/2023 | APPROVED |
12/08/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/10/2023 | REQUIRES RESUBMIT |
09/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/12/2023 | APPROVED |
04/03/2023 | COMMERCIAL REVIEW - FULL v.3 | 04/07/2023 | APPROVED |
10/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/16/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1122-00154
Permit Status: Complete
Permit Description: New Commercial Shell building
Date | Description | Comments |
---|---|---|
01/10/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
01/10/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
01/10/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. (NOTE: Project Architect Gene Goldstein confirmed epoxy anchor special inspection is not required, see submitted letter.) | |
01/10/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.(NOTE: Project Architect Gene Goldstein confirmed expansion anchor special inspection is not required, see submitted letter.) | |
01/10/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
09/12/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
01/10/2023 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
01/10/2023 | WATER STERILIZATION REPORT IS REQUIRED. (NOTE: Water sterilization report was submitted under the TI permit, TC-COM-0623-01456 as that work was not a part of the scope for the shell building) ) |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00154
Permite Description: New Commercial Shell building
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/14/2023 | BULD - Electrical Clearance | N/A | Canceled | |
09/25/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | No gas to this location. |
06/13/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
06/21/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | Main service underground is in. Okay to set transformer pad. Electrical panels are installed and being piped to ceiling and exterior walls. Okay to proceed with electrical work. |
09/25/2023 | COT - HCPL - Backwater Valve | N/A | Not Applicable | Not required. |
05/19/2023 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | Partial pass. Looked at 9 light pole bases. Rebar per plans UFER is in place. Okay for concrete placement. 5/19/2023 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00154
Permit Description: New Commercial Shell building
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2023 | COT - HCPL - Rough Soil | Passed | Rough plumbing is complete for this phase of construction. | |
04/28/2023 | COT - HCBU - Building Progress | Passed | Footing are complete. Red iron steel is in place. Roof trusses are installed and plywood is properly nailed off. | |
04/28/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | All trusses are properly connected to top plates with H2.5 Simpson connectors. All exterior shear walls are properly screwed off. | |
04/28/2023 | COT - HCBU - Framing | Passed | Exterior framing is complete. All exterior shear walls are properly screwed off. | |
04/28/2023 | COT - HCBU - Roof Nailing | Passed | Roof is properly nailed off. | |
06/14/2023 | COT - HCPL - Sewer | Passed | Sewer connection is made at main sewer line. | |
06/14/2023 | COT - HCPL - Plumbing Intermediate | Passed | Water lines for hose bibs are installed. No other plumbing at this time, this is only a shell building TI will complete rest of plumbing. | |
06/14/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Footings match construction plans and are 12" thick. | |
07/24/2023 | BULD - Electrical Clearance | Passed | 600A service, ECO Clearance is required to TEP is required | |
09/25/2023 | COT - HCEL - Electrical Final | Passed | Electrical power is complete, energized and fully functional for the building. | |
09/25/2023 | COT - HCPL - Plumbing Final | Passed | Construction of Tenant Improvements is complete. Electrical, mechanical, and plumbing fixtures and equipment is installed and fully functional. Interior booths, tables, and chairs are in place in lobby area. All Starbucks equipment is installed and operational. Restrooms have ADA accessible hardware installed. Fire has completed there inspection. Health is scheduled for tomorrow to perform their inspection. Okay to issue Level 4 Certificate of Occupancy once all required inspections are completed. | |
09/25/2023 | COT - HCME - Mechanical Final | Passed | Construction of Tenant Improvements is complete. Electrical, mechanical, and plumbing fixtures and equipment is installed and fully functional. Interior booths, tables, and chairs are in place in lobby area. All Starbucks equipment is installed and operational. Restrooms have ADA accessible hardware installed. Fire has completed there inspection. Health is scheduled for tomorrow to perform their inspection. Okay to issue Level 4 Certificate of Occupancy once all required inspections are completed. | |
09/25/2023 | COT - HCBU - Building Final | Passed | Shell building is fully complete. | |
09/25/2023 | COT - FCON - Fire - Final | Passed | ||
09/25/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
09/25/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
09/25/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
09/25/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
09/25/2023 | COT - HCEL - Electrical Progress | Passed | ||
09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
09/25/2023 | COT - HCME - Mechanical Progress | Passed | ||
09/25/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
09/25/2023 | COT - HCPL - Plumbing Progress | Passed | ||
09/25/2023 | COT - HCPL - Plumbing Roof Drains | Passed | ||
09/26/2023 | COT - HCEL - Outdoor Lighting | Passed | 9/25/23: Outdoor Lighting is complete and operational. | |
09/26/2023 | COT - HCME - Mechanical Intermediate | Passed |