Permit: TC-COM-1025-01903
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1028 N COUNTRY CLUB RD
Address NEW:
1028 N COUNTRY CLUB RD
Apply Date:
10/14/2025
Applicant:
Cathy Lane
Description:
Install New Diesel generator on new 4'x9' Concrete pad. Add new chain-link fence w gate. Add ATS and conduit from existing equipment area.
Permit Reviews
Permit Number - TC-COM-1025-01903
Permit Status: Complete
Permit Description: Install New Diesel generator on new 4'x9' Concrete pad. Add new chain-link fence w gate. Add ATS and conduit from existing equipment area.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/15/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 10/31/2025 | REQUIRES RESUBMIT |
| 12/17/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 12/24/2025 | APPROVED |
Conditions
Permit Number - TC-COM-1025-01903
Permit Status: Complete
Permit Description: Install New Diesel generator on new 4'x9' Concrete pad. Add new chain-link fence w gate. Add ATS and conduit from existing equipment area.
| Date | Description | Comments |
|---|---|---|
| 12/19/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 10/15/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1025-01903
Permite Description: Install New Diesel generator on new 4'x9' Concrete pad. Add new chain-link fence w gate. Add ATS and conduit from existing equipment area.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2026 | ENGR Engineering Final | N/A | Not Ready | Fence not built. Asphalt not patched where cut for conduit was made. Reschedule when project is complete. |
| 03/27/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | OP for diesel tank. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1025-01903
Permit Description: Install New Diesel generator on new 4'x9' Concrete pad. Add new chain-link fence w gate. Add ATS and conduit from existing equipment area.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2026 | COT - HCBU - Preslab | Passed | Reinforcements along with depths per plan. Okay for concrete placement. 2/27/2026 | |
| 02/27/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Reinforcements along with depths per plan. Okay for concrete placement. 2/27/2026 | |
| 03/12/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/12/2026 | COT - LCEL - Electrical Intermediate | Passed | ||
| 03/12/2026 | COT - LCEL - Electrical Underground | Passed | ||
| 03/27/2026 | COT - HCBU - Building Final | Passed | ||
| 03/27/2026 | COT - HCEL - Electrical Final | Passed | ||
| 03/27/2026 | ENGR Engineering Final | Passed | ||
| 04/15/2026 | COT - FCON - Fire - Final | Passed |