Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
10/18/2024
Applicant:
Kelly Rehm
Description:
The Pantano Christian Church PV2 system (46.28kW DC) consists of 89 520W PV modules. 23 grid-tied microinverters will supply power through an existing TEP service. All modules are to be roof-mounted.

Permit Reviews

Permit Number - TC-COM-1024-02000
Permit Status: Complete
Permit Description: The Pantano Christian Church PV2 system (46.28kW DC) consists of 89 520W PV modules. 23 grid-tied microinverters will supply power through an existing TEP service. All modules are to be roof-mounted.
Start Date Submittal Complete Date Status  
10/21/2024 COMMERCIAL REVIEW - FULL v.1 11/14/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1024-02000
Permite Description: The Pantano Christian Church PV2 system (46.28kW DC) consists of 89 520W PV modules. 23 grid-tied microinverters will supply power through an existing TEP service. All modules are to be roof-mounted.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
02/12/2025 COT - FCON - Fire - Final N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1024-02000
Permit Description: The Pantano Christian Church PV2 system (46.28kW DC) consists of 89 520W PV modules. 23 grid-tied microinverters will supply power through an existing TEP service. All modules are to be roof-mounted.
Total Completed Inspections - 7
Date Description Inspector Results Comments
02/12/2025 COT - CSOL - Electrical Final Solar Project Passed
02/12/2025 COT - LCBU - Building Final Passed
02/12/2025 ENGR Engineering Final Passed
02/12/2025 TRSP - ROW - Final/Close-Out Passed All work was done on private property to install solar panels on the church rooftop.
02/12/2025 COT - CSOL - Electrical Underground Solar Project Passed
02/12/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
02/12/2025 BULD - Electrical Clearance Passed Approved 3-phase solar installation - DGC Clearance to TEP is required for the solar meter