Permit: TC-COM-1023-02525
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1500 W COMMERCE CT BLDG 2
Address NEW:
1500 W COMMERCE CT BLDG 2
Apply Date:
10/26/2023
Applicant:
Colton Lloyd
Description:
N/A
Permit Reviews
Permit Number - TC-COM-1023-02525
Permit Status: Complete
Permit Description:
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/08/2023 | RESTAMP - COMMERCIAL v.1 | 12/11/2023 | APPROVED |
| 12/06/2023 | COMMERCIAL REVIEW - FULL v.3 | 12/08/2023 | APPROVED |
| 11/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/01/2023 | REQUIRES RESUBMIT |
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/31/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1023-02525
Permit Status: Complete
Permit Description:
| Date | Description | Comments |
|---|---|---|
| 10/31/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1023-02525
Permite Description:
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/17/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 03/04/2024 | BULD - Electrical Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1023-02525
Permit Description:
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/01/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
| 02/01/2024 | COT - HCEL - Electrical Underground | Passed | 2/1/24: electrical underground for X-ray per plan ok to backfill. | |
| 02/14/2024 | COT - HCEL - Electrical Intermediate | Passed | 2/14/24: electrical in wall passed in x-ray room and storage. rooms 116 and 124 | |
| 02/14/2024 | COT - HCME - Mechanical Intermediate | Passed | 2/14/24: supply duct and return air run offs per plan ok to proceed. | |
| 02/14/2024 | COT - HCPL - Plumbing Intermediate | Passed | 2/14/24: plumbing intermediate at x-ray room per plan. Passed | |
| 02/14/2024 | COT - HCBU - Framing | Passed | ||
| 03/04/2024 | COT - FCON - Fire - Final | Passed | ||
| 03/04/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 03/04/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 03/04/2024 | ENGR Engineering Final | Passed | Tenant finish, all interior, CO ready | |
| 03/05/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/04/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 03/04/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 03/04/2024 | COT - HCME - Mechanical Final | Passed | ||
| 03/04/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 03/04/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 04/16/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 04/16/2024 | COT - HCBU - Building Final | Passed | ||
| 04/16/2024 | COT - HCEL - Electrical Final | Passed |