Permit: TC-COM-0924-01874
Permit Details
Apply Date:
09/26/2024
Applicant:
Austin Petrick
Description:
Ground-up automotive maintenance building.
Permit Reviews
Permit Number - TC-COM-0924-01874
Permit Status: Complete
Permit Description: Ground-up automotive maintenance building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/18/2025 | APPROVED |
| 09/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/30/2025 | APPROVED |
| 01/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/31/2025 | APPROVED |
| 12/31/2024 | RESTAMP - COMMERCIAL v.1 | 01/03/2025 | APPROVED |
| 12/11/2024 | COMMERCIAL REVIEW - FULL v.3 | 12/31/2024 | APPROVED |
| 11/12/2024 | COMMERCIAL REVIEW - FULL v.2 | 11/25/2024 | REQUIRES RESUBMIT |
| 01/14/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/15/2025 | APPROVED |
| 07/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 07/17/2025 | APPROVED |
| 10/02/2024 | COMMERCIAL REVIEW - FULL v.1 | 10/31/2024 | REQUIRES RESUBMIT |
| 07/10/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/10/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0924-01874
Permit Status: Complete
Permit Description: Ground-up automotive maintenance building.
| Date | Description | Comments |
|---|---|---|
| 10/31/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 01/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 10/11/2024 | SPECIAL INSPECTION OF FABRICATORS IS REQUIRED. | |
| 12/31/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 10/11/2024 | SPECIAL INSPECTION FOR POST-INSTALLED ANCHORS IS REQUIRED. | |
| 10/11/2024 | Pre-Engineered Metal Building Design, Calculations and Construction Drawings, prepared by an Arizona licensed Registrant, must be submitted and approved prior to Final Inspection | |
| 12/31/2024 | Please submit a separate sign permit for an signs associated with this projet. | |
| 12/11/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 10/11/2024 | SPECIAL INSPECTION FOR SOIL IS REQUIRED. | |
| 12/31/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 12/31/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 10/11/2024 | SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED. | |
| 10/31/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0924-01874
Permite Description: Ground-up automotive maintenance building.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2025 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | |
| 07/18/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0924-01874
Permit Description: Ground-up automotive maintenance building.
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2025 | COT - LCPL - Sewer | Passed | ||
| 02/11/2025 | COT - LCPL - Rough Soil | Passed | ||
| 03/03/2025 | COT - LCBU - Preslab | Passed | ||
| 04/03/2025 | COT - LCPL - Yard Water Line | Passed | From the building heading north 20 feet connecting to backflow, backflow orientation is east and flow heading west, from backflow pipe goes west 15 feet to a 90 degree bend under curb in island, then heads 5 feet north on opposite side of curb from island okay to back fill. Shading is required. 4/3/2025 | |
| 07/18/2025 | BULD - Electrical Clearance | Passed | ||
| 07/18/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 07/18/2025 | COT - LCEL - Electrical Progress | Passed | ||
| 08/12/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 08/12/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 08/12/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 08/12/2025 | COT - LCBU - Framing | Passed | ||
| 08/12/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 08/15/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 08/15/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 08/15/2025 | COT - LCPL - Plumbing Roof Drains | Passed | ||
| 08/15/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 08/15/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/21/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/21/2025 | COT - LCEL - Electrical Final | Passed | ||
| 08/21/2025 | COT - LCME - Mechanical Final | Passed | ||
| 08/21/2025 | ENGR Engineering Final | Passed | ||
| 10/01/2025 | COT - LCEL - Outdoor Lighting | Passed | ||
| 10/01/2025 | COT - LCBU - Building Final | Passed |