Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Commercial Building
Apply Date:
09/07/2023
Applicant:
Jesus Martinez
Description:
Wall for TEP DeMoss Petrie Substation. CMU wall built around the substation. NO Uility work such as Electric on this permit. (1000000.00) Project Engineer: Gannon McGhee, gmcghee@tep.com, (520) 745-3126 Project Manager: Doyace Wilson, dwilson@tep.com, (520) 528-7450.

Permit Reviews

Permit Number - TC-COM-0923-02166
Permit Status: Inspections
Permit Description: Wall for TEP DeMoss Petrie Substation. CMU wall built around the substation. NO Uility work such as Electric on this permit. (1000000.00) Project Engineer: Gannon McGhee, gmcghee@tep.com, (520) 745-3126 Project Manager: Doyace Wilson, dwilson@tep.com, (520) 528-7450.
Start Date Submittal Complete Date Status  
11/16/2023 COMMERCIAL REVIEW - FULL v.2 11/17/2023 REQUIRES RESUBMIT Review Details
07/26/2024 RESTAMP - COMMERCIAL v.1 08/01/2024 APPROVED Review Details
06/28/2024 COMMERCIAL REVIEW - FULL v.4 07/26/2024 APPROVED Review Details
09/11/2023 COMMERCIAL REVIEW - FULL v.1 10/09/2023 REQUIRES RESUBMIT Review Details
02/05/2024 COMMERCIAL REVIEW - FULL v.3 02/27/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0923-02166
Permit Status: Inspections
Permit Description: Wall for TEP DeMoss Petrie Substation. CMU wall built around the substation. NO Uility work such as Electric on this permit. (1000000.00) Project Engineer: Gannon McGhee, gmcghee@tep.com, (520) 745-3126 Project Manager: Doyace Wilson, dwilson@tep.com, (520) 528-7450.
Total Outstanding Activity Conditions - 3
Date Name
08/20/2024 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
08/20/2024 Masonry Inspection Report submittal review is required.
08/20/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.

Conditions

Permit Number - TC-COM-0923-02166
Permit Status: Inspections
Permit Description: Wall for TEP DeMoss Petrie Substation. CMU wall built around the substation. NO Uility work such as Electric on this permit. (1000000.00) Project Engineer: Gannon McGhee, gmcghee@tep.com, (520) 745-3126 Project Manager: Doyace Wilson, dwilson@tep.com, (520) 528-7450.
Date Description Comments
09/08/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0923-02166
Permite Description: Wall for TEP DeMoss Petrie Substation. CMU wall built around the substation. NO Uility work such as Electric on this permit. (1000000.00) Project Engineer: Gannon McGhee, gmcghee@tep.com, (520) 745-3126 Project Manager: Doyace Wilson, dwilson@tep.com, (520) 528-7450.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
06/25/2025 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass Screen wall footing (Northwest). approximately 75’ at 8’ x 16”. Electric ufers are in place. Ok to place concrete in progress areas.
08/19/2025 COT - LCBU - Masonry Pregrout N/A Partial Pass 8/19/2025 1st lift north west corner on west wall going south. 2nd lift 8' from northwest corner on west wall going south. Approved per third party report.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-21-191 FINAL DRAWING SET - REV 02 - 6-25-24_V3.PDF DOCUMENTS VIEW
CONS-21-191 FINAL DRAWING SET 11-01-22_V1.PDF DOCUMENTS VIEW