Permit: TC-COM-0724-01333
Permit Details
Apply Date:
07/10/2024
Applicant:
Dana Robinson
Description:
Maintenance & paint will be performed. Replacement of registers with new, pre-built moveable units, along with the replacement of the existing power poles using the same circuits. Reach-in coolers & freezers will be replaced with new, self-contained plug-in units with new circuits and outlets.
Permit Reviews
Permit Number - TC-COM-0724-01333
Permit Status: Issued
Permit Description: Maintenance & paint will be performed. Replacement of registers with new, pre-built moveable units, along with the replacement of the existing power poles using the same circuits. Reach-in coolers & freezers will be replaced with new, self-contained plug-in units with new circuits and outlets.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/11/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 07/31/2024 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0724-01333
Permite Description: Maintenance & paint will be performed. Replacement of registers with new, pre-built moveable units, along with the replacement of the existing power poles using the same circuits. Reach-in coolers & freezers will be replaced with new, self-contained plug-in units with new circuits and outlets.
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/27/2024 | COT - FCON - Fire - Final | N/A | Not Applicable | Moved cooler from one side of the store to the other. |
08/27/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
08/27/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
08/27/2024 | COT - LCPL - Plumbing Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0724-01333
Permit Description: Maintenance & paint will be performed. Replacement of registers with new, pre-built moveable units, along with the replacement of the existing power poles using the same circuits. Reach-in coolers & freezers will be replaced with new, self-contained plug-in units with new circuits and outlets.
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/27/2024 | ENGR Engineering Final | Passed | ||
08/27/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
08/27/2024 | COT - LCEL - Electrical Final | Passed | ||
08/27/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
08/27/2024 | COT - LCME - Mechanical Final | Passed | ||
08/27/2024 | COT - LCBU - Building Final | Passed | ||
08/27/2024 | COT - LCEL - Electrical Intermediate | Passed |