Permit: TC-COM-0723-01819
Permit Details
Apply Date:
07/26/2023
Applicant:
Kyle Vilaubi
Description:
New Shell Building for future Starbucks
Permit Reviews
Permit Number - TC-COM-0723-01819
Permit Status: Complete
Permit Description: New Shell Building for future Starbucks
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/01/2023 | REQUIRES RESUBMIT |
| 12/19/2023 | RESTAMP - COMMERCIAL v.1 | 12/20/2023 | APPROVED |
| 07/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/17/2024 | APPROVED |
| 12/18/2023 | RESTAMP - COMMERCIAL v.1 | 12/19/2023 | IN REVIEW |
| 11/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/18/2023 | APPROVED |
| 08/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/16/2024 | APPROVED |
| 08/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/08/2024 | APPROVED |
| 03/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/25/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0723-01819
Permit Status: Complete
Permit Description: New Shell Building for future Starbucks
| Date | Description | Comments |
|---|---|---|
| 08/08/2024 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. | |
| 07/27/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/08/2024 | SPECIAL INSPECTION FOR EARTHWORK IS REQUIRED. | |
| 08/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 07/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 08/08/2024 | SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED. | |
| 08/08/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01819
Permite Description: New Shell Building for future Starbucks
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 07/11/2024 | COT - HCME - Venting | N/A | Not Applicable | |
| PDSD Heavy Commercial Building Division Pre-Construction Meeting | N/A | Requested | ||
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 07/16/2024 | COT - HCME - Mechanical Final | N/A | Re-inspection required | Install roof access ladder. |
| 07/24/2024 | ENGR Engineering Final | N/A | Not Ready | There are a few items that need to be redone. 1) ADA ramp from parking area needs to be one pitch from flat to flat. 2) ADA also needs to have rails on both sides of lower and one side of upper. 3) There is a dbl pitch in the patio area going to the walkway that needs to also to be redone. 4) Short term bike parking needs to be a 6' slab so the bikes won't impede the walkway. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01819
Permit Description: New Shell Building for future Starbucks
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/14/2024 | COT - HCPL - Rough Soil | Passed | Grease interceptor is installed and connected to underground plumbing. Underground plumbing is installed and under a water test with no leaks. Okay to backfill trenches and grease interceptor. | |
| 02/21/2024 | COT - HCEL - Grounding/Bonding | Passed | Ufer ground wire is properly secured to the bottom 20' piece of rebar reinforcement. Okay to cover with concrete. | |
| 02/21/2024 | COT - HCEL - Electrical Underground | Passed | Electrical conduit for underground electrical is properly installed for electrical and communication wiring. Okay to backfill trenches. | |
| 03/07/2024 | COT - HCBU - Preslab | Passed | ||
| 04/12/2024 | COT - HCBU - Framing | Passed | Metal stud framing complete for exterior walls, wood framing partially completed for parapet walls around roof. Exterior sheathing for shear wall is properly screwed to studs at 7" on edge and 12" in field. | |
| 04/16/2024 | COT - HCBU - Roof Nailing | Passed | Ok to,dry in roof system. | |
| 04/22/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | Exterior shear walls are properly secured to metal studs at 7" on edge and 12" in the field. Okay to proceed with window installation and dry-in of exterior walls for stucco application. | |
| 05/13/2024 | COT - HCEL - Outdoor Lighting | Passed | Not ready for this inspection, needed rebar and footing inspection for light pole bases. | |
| 05/13/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Footings and rebar for exterior light poles are properly dug, rebar reinforcement cages are installed, and Ufer ground is in place from bottom of footings to top of rebar cage. Okay to pour concrete light pole bases. | |
| 05/14/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
| 05/16/2024 | COT - HCEL - Electrical Progress | Passed | Ok to insulate and sheet rock interior walls | |
| 05/16/2024 | COT - HCPL - Plumbing Progress | Passed | Ok to insulate and sheet rock interior walls. | |
| 06/03/2024 | BULD - Electrical Clearance | Passed | ||
| 06/04/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 06/04/2024 | COT - HCBU - Building Progress | Passed | ||
| 06/04/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 06/04/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 06/04/2024 | COT - HCME - Mechanical Underground | Passed | ||
| 07/01/2024 | COT - HCBU - Masonry Pregrout | Passed | Trash enclosure and patio area. Okay to fully grout. Top out. 7/1/2024 | |
| 07/11/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 07/11/2024 | COT - HCEL - Electrical Final | Passed | ||
| 07/11/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 07/11/2024 | COT - HCME - Mechanical Progress | Passed | ||
| 07/11/2024 | COT - HCPL - Backwater Valve | Passed | ||
| 07/11/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 07/11/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 07/16/2024 | COT - HCPL - Gas Final | Passed | ||
| 07/16/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 07/24/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 07/24/2024 | COT - FCON - Fire - Final | Passed | ||
| 07/24/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 07/24/2024 | COT - HCME - Mechanical Final | Passed | ||
| 07/24/2024 | COT - HCBU - CofO | Passed | 7/24/24: shell building completed | |
| 08/02/2024 | COT - HCBU - Building Final | Passed | ||
| 09/26/2024 | ENGR Engineering Final | Passed | This venue opened on the week of the 16th without a final inspection from engineering. CO is approved it should have been completed prior to the pending and release of the CO. |