Permit: TC-COM-0723-01791
Permit Details
Apply Date:
07/20/2023
Applicant:
Garett Cunningham
Description:
Watermill Express kiosk free standing, unmanned water & ice vending stations in two, leased shopping plaza parking spaces. Each kiosk is a fully premanufactured unit that has been inspected, approved, and stamped at the state level, leaving only the foundation and plumbing & electrical connections reviewable and inspected on the local level. REV1: Sheets being submitted were lost during processing. They were originally submitted with the original submittal but never picked up in subsequent reviews.
Permit Reviews
Permit Number - TC-COM-0723-01791
Permit Status: Complete
Permit Description: Watermill Express kiosk free standing, unmanned water & ice vending stations in two, leased shopping plaza parking spaces.
Each kiosk is a fully premanufactured unit that has been inspected, approved, and stamped at the state level, leaving only the foundation and plumbing & electrical connections reviewable and inspected on the local level.
REV1: Sheets being submitted were lost during processing. They were originally submitted with the original submittal but never picked up in subsequent reviews.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/08/2024 | COMMERCIAL REVIEW - FULL v.5 | 12/05/2024 | REQUIRES RESUBMIT |
| 08/27/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/28/2025 | APPROVED |
| 11/09/2023 | COMMERCIAL REVIEW - FULL v.3 | 12/12/2023 | REQUIRES RESUBMIT |
| 02/04/2025 | RESTAMP - COMMERCIAL v.1 | 02/04/2025 | APPROVED |
| 07/26/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/29/2023 | REQUIRES RESUBMIT |
| 02/04/2025 | COMMERCIAL REVIEW - FULL v.6 | 02/04/2025 | APPROVED |
| 03/12/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/03/2025 | APPROVED |
| 01/25/2024 | COMMERCIAL REVIEW - FULL v.4 | 01/25/2024 | REQUIRES RESUBMIT |
| 07/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/25/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0723-01791
Permit Status: Complete
Permit Description: Watermill Express kiosk free standing, unmanned water & ice vending stations in two, leased shopping plaza parking spaces.
Each kiosk is a fully premanufactured unit that has been inspected, approved, and stamped at the state level, leaving only the foundation and plumbing & electrical connections reviewable and inspected on the local level.
REV1: Sheets being submitted were lost during processing. They were originally submitted with the original submittal but never picked up in subsequent reviews.
| Date | Description | Comments |
|---|---|---|
| 06/25/2024 | Please contact Pima County Addressing to verify official address. Addressing@pima.gov or 520-724-9512 | |
| 08/29/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/04/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 11/14/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01791
Permit Description: Watermill Express kiosk free standing, unmanned water & ice vending stations in two, leased shopping plaza parking spaces.
Each kiosk is a fully premanufactured unit that has been inspected, approved, and stamped at the state level, leaving only the foundation and plumbing & electrical connections reviewable and inspected on the local level.
REV1: Sheets being submitted were lost during processing. They were originally submitted with the original submittal but never picked up in subsequent reviews.
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2025 | COT - LCBU - Preslab | Passed | 3-19-25, reinforcement for preslab verified per approved plans. Okay to pour concrete. | |
| 07/22/2025 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 7/22/2025 | |
| 08/19/2025 | COT - LCEL - Electrical Final | Passed | ||
| 08/19/2025 | COT - LCBU - Building Final | Passed | ||
| 08/19/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 08/20/2025 | COT - HCBU - CofO | Passed | ||
| 08/21/2025 | ENGR Engineering Final | Passed | Site is clear and complete. | |
| 08/21/2025 | COT - HCEL - Outdoor Lighting | Passed | ||
| 08/21/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 08/21/2025 | COT - LCPL - Sewer | Passed | ||
| 08/21/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 08/21/2025 | COT - LCPL - Yard Water Line | Passed | ||
| 08/21/2025 | COT - LCEL - Grounding/Bonding | Passed |