Permit: TC-COM-0723-01696
Permit Details
Apply Date:
07/13/2023
Applicant:
Michael Epstein
Description:
Electrical service AND SYSTEMS upgrade including EXTERIOR cable trays for wiring to manufacturing floor.
Permit Reviews
Permit Number - TC-COM-0723-01696
Permit Status: Complete
Permit Description: Electrical service AND SYSTEMS upgrade including EXTERIOR cable trays for wiring to manufacturing floor.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/10/2023 | RESTAMP - COMMERCIAL v.1 | 08/11/2023 | APPROVED |
08/09/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/10/2023 | APPROVED |
07/13/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/07/2023 | REQUIRES RESUBMIT |
12/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/23/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0723-01696
Permit Status: Complete
Permit Description: Electrical service AND SYSTEMS upgrade including EXTERIOR cable trays for wiring to manufacturing floor.
Date | Description | Comments |
---|---|---|
12/22/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
07/20/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
12/22/2023 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
12/22/2023 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
12/22/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01696
Permite Description: Electrical service AND SYSTEMS upgrade including EXTERIOR cable trays for wiring to manufacturing floor.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2023 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | Column footings. |
01/03/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
01/03/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 1/3/23: called at 9:52am and left message stating that I was 15 min out. Called at 10:11am and arrived onsite. No answer 1/3/23: Service Entrance Panel SDS-4 passed. Pending connection to transformer, supports of feeders going into building per plan ok to proceed. |
01/03/2024 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 1/3/23: called at 9:52am and left message stating that I was 15 min out. Called at 10:11am and arrived onsite. No answer 1/3/23: Service Entrance Panel SDS-4 passed. Pending connection to transformer, supports of feeders going into building per plan ok to proceed. |
11/15/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 45’ of 12 4” conduit. Electrical underground. Secondaries. Okay to backfill. Shading required. 11/15/2023 |
03/13/2024 | COT - HCEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01696
Permit Description: Electrical service AND SYSTEMS upgrade including EXTERIOR cable trays for wiring to manufacturing floor.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/29/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
01/09/2024 | ENGR Engineering Final | Passed | ||
01/09/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
01/12/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
01/12/2024 | COT - HCEL - Electrical Progress | Passed | ||
01/12/2024 | COT - HCEL - Electrical Underground | Passed | ||
01/16/2024 | BULD - Electrical Clearance | Passed | Approved new 4000A SES, ECO Clearance to TEP is required for meter #3M 1/22/24 clearance resent |
|
04/05/2024 | COT - HCEL - Electrical Final | Passed |