Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Address:
400 S SARNOFF DR
Address NEW:
400 S SARNOFF DR
Apply Date:
06/24/2025
Applicant:
gilbert alabado
Description:
Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.

Permit Reviews

Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Start Date Submittal Complete Date Status  
11/09/2026 SPECIAL INSPECTION REVIEW v.1 N/A REQUIRES RESUBMIT Review Details
08/01/2025 COMMERCIAL REVIEW - LIMITED v.3 08/06/2025 APPROVED Review Details
08/06/2025 RESTAMP - COMMERCIAL v.1 08/07/2025 APPROVED Review Details
07/11/2025 COMMERCIAL REVIEW - LIMITED v.2 07/28/2025 REQUIRES RESUBMIT Review Details
06/27/2025 COMMERCIAL REVIEW - LIMITED v.1 06/27/2025 REQUIRES RESUBMIT Review Details
03/23/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/24/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Outstanding Activity Conditions - 7
Date Name
07/23/2025 PRE-FABRICATED RESTROOM SHALL BE PERMITTED THROUGH THE ARIZONA DEPARTMENT OF HOUSING (ADH) BY THE CONTRACTOR. (***Submit a copy of the State approved Construction Drawings and a copy of the State issued Installation Plan Approval.)
08/06/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/06/2025 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
08/06/2025 A Special Inspections Intermediate Certificate must be submitted as a deferred submittal..
08/06/2025 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
08/06/2025 WATER STERILIZATION REPORT IS REQUIRED.
08/06/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Date Description Comments
08/06/2025 The ramada will be submitted by the contractor as a Deferred Submittal. The structural calcs and any additional details will be submitted by the Ramada Certified Installer/vendor (sub-contractor). The manufacturer will not provide structural plans and calculations until the pre-engineered Ramada have been purchased. (***Submit a copy of the State approved Construction Drawings and a copy of the State issued Installation Plan Approval.)
06/27/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0625-01226
Permite Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
03/18/2026 COT - LCPL - Sewer N/A Partial Pass West side.
03/24/2026 COT - LCPL - Yard Water Line N/A Partial Pass Partial pass for water line connection
04/14/2026 TRSP - ROW - Notice of Completion N/A Re-inspection required
12/10/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 12/10/25: rebar cage and cast in place anchors for shade columns (4) approved at south west shade structure. Reinforcement and depth of shafts per approved plans ok to proceed with concrete placement.
08/26/2026 COT - LCPL - Plumbing Final N/A Re-inspection required Clear permit conditions.

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0625-01226
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/19/2026 COT - LCPL - Sewer Passed
08/26/2026 COT - LCPL - Rough Soil Passed
09/03/2026 COT - LCEL - Electrical Underground Passed Electrical underground for Transformer secondary from south side of the building running about 100 feet south to transformer pad.
09/15/2026 BULD - Electrical Clearance Passed TEP CLEARANCE: CECM
Manufactured Building/Restroom

Documents

File Name Document Type  
93075 GABLE EX 30' X 30' - ENGINEERING_V1.PDF DOCUMENTS VIEW
93075 GABLE EX 30' X 30' - INSTALL_SEALED_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-24-1274-JO-PLAY-RR-100-BUILDINGPLAN-RESUBMITTAL_V3.PDF DOCUMENTS VIEW
25-1978_JESSEOWENSPARK-HIPPED-FINAL-CALCS-SIGNED_V3.PDF DOCUMENTS VIEW
606855001 R JESSE OWENS - ADDENDUM NO. 1-SCAN_V3.PDF DOCUMENTS VIEW
JO-PARK-PLAY-RR-100SEALED-SPECS-250514_V3.PDF DOCUMENTS VIEW