Permit: TC-COM-0625-01226
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
400 S SARNOFF DR
Address NEW:
400 S SARNOFF DR
Apply Date:
06/24/2025
Applicant:
gilbert alabado
Description:
Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Permit Reviews
Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/09/2026 | SPECIAL INSPECTION REVIEW v.1 | N/A | REQUIRES RESUBMIT |
| 08/01/2025 | COMMERCIAL REVIEW - LIMITED v.3 | 08/06/2025 | APPROVED |
| 08/06/2025 | RESTAMP - COMMERCIAL v.1 | 08/07/2025 | APPROVED |
| 07/11/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 07/28/2025 | REQUIRES RESUBMIT |
| 06/27/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 06/27/2025 | REQUIRES RESUBMIT |
| 03/23/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/24/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 07/23/2025 | PRE-FABRICATED RESTROOM SHALL BE PERMITTED THROUGH THE ARIZONA DEPARTMENT OF HOUSING (ADH) BY THE CONTRACTOR. (***Submit a copy of the State approved Construction Drawings and a copy of the State issued Installation Plan Approval.) |
| 08/06/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/06/2025 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
| 08/06/2025 | A Special Inspections Intermediate Certificate must be submitted as a deferred submittal.. |
| 08/06/2025 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
| 08/06/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
| 08/06/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0625-01226
Permit Status: Needs resubmittal
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
| Date | Description | Comments |
|---|---|---|
| 08/06/2025 | The ramada will be submitted by the contractor as a Deferred Submittal. The structural calcs and any additional details will be submitted by the Ramada Certified Installer/vendor (sub-contractor). The manufacturer will not provide structural plans and calculations until the pre-engineered Ramada have been purchased. (***Submit a copy of the State approved Construction Drawings and a copy of the State issued Installation Plan Approval.) | |
| 06/27/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0625-01226
Permite Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2026 | COT - LCPL - Sewer | N/A | Partial Pass | West side. |
| 03/24/2026 | COT - LCPL - Yard Water Line | N/A | Partial Pass | Partial pass for water line connection |
| 04/14/2026 | TRSP - ROW - Notice of Completion | N/A | Re-inspection required | |
| 12/10/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 12/10/25: rebar cage and cast in place anchors for shade columns (4) approved at south west shade structure. Reinforcement and depth of shafts per approved plans ok to proceed with concrete placement. |
| 08/26/2026 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | Clear permit conditions. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0625-01226
Permit Description: Jesse Owens Park Improvements include new pre-fabricated restroom, new ramada and new hip shade structure.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | COT - LCPL - Sewer | Passed | ||
| 08/26/2026 | COT - LCPL - Rough Soil | Passed | ||
| 09/03/2026 | COT - LCEL - Electrical Underground | Passed | Electrical underground for Transformer secondary from south side of the building running about 100 feet south to transformer pad. | |
| 09/15/2026 | BULD - Electrical Clearance | Passed | TEP CLEARANCE: CECM Manufactured Building/Restroom |