Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
5530 E BROADWAY BL
Apply Date:
06/12/2025
Applicant:
Heather Newman
Description:
Interior Remodel, Including Interior Partitions, New Lighting, New Ceiling, New Kitchenette and Associated MEP Systems

Permit Reviews

Permit Number - TC-COM-0625-01151
Permit Status: Complete
Permit Description: Interior Remodel, Including Interior Partitions, New Lighting, New Ceiling, New Kitchenette and Associated MEP Systems
Start Date Submittal Complete Date Status  
12/12/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/17/2025 APPROVED Review Details
11/20/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/24/2025 APPROVED Review Details
09/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/05/2025 APPROVED Review Details
07/30/2025 COMMERCIAL REVIEW - FULL v.2 07/30/2025 REQUIRES RESUBMIT Review Details
07/31/2025 COMMERCIAL REVIEW - FULL v.3 08/22/2025 APPROVED Review Details
06/18/2025 COMMERCIAL REVIEW - FULL v.1 07/09/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0625-01151
Permit Status: Complete
Permit Description: Interior Remodel, Including Interior Partitions, New Lighting, New Ceiling, New Kitchenette and Associated MEP Systems
Date Description Comments
07/08/2025 AIR BALANCING REPORT IS REQUIRED.
12/15/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/18/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
12/15/2025 Masonry Inspection Report submittal review is required.
07/08/2025 NESHAP Permit is required. (Utilized with commercial demolition permits)
08/19/2025 SPECIAL INSPECTION OF ALL ANCHORS AND/OR CONNECTIONS INSTALLED IN CONCRETE MASONRY UNIT WALLS.
08/19/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
12/15/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0625-01151
Permite Description: Interior Remodel, Including Interior Partitions, New Lighting, New Ceiling, New Kitchenette and Associated MEP Systems
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
09/29/2025 COT - LCBU - Stem Wall/Retaining Wall N/A Partial Pass Refuse enclosure, footer: dimensions and reinforcement are good. Okay to pour.
10/06/2025 COT - LCBU - Masonry Pregrout N/A Canceled wanted dumpster enclosure
10/09/2025 COT - LCPL - Plumbing Intermediate N/A Not Ready
10/28/2025 BULD - Electrical Clearance N/A Not Applicable
10/28/2025 COT - BULD - SWG Clearance N/A Not Applicable
11/13/2025 COT - LCPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0625-01151
Permit Description: Interior Remodel, Including Interior Partitions, New Lighting, New Ceiling, New Kitchenette and Associated MEP Systems
Total Completed Inspections - 16
Date Description Inspector Results Comments
09/18/2025 COT - LCME - Mechanical Intermediate Passed
09/29/2025 COT - LCBU - Excavation/Rebar/Zoning Passed looked at structural components of footing; requested builder to schedule with engineering group. Also looked at electric intermediate at offices; requested builder to schedule.
10/01/2025 COT - LCBU - Framing Passed
10/07/2025 COT - LCPL - Rough Soil Passed
10/07/2025 For trash and recycling enclosures Passed 10/7/25
Bond beam in with 2 #4 bond beam in place. Horizontal reinforcement correct.
Okay to pour grout to bond beam and finish wall.
10/10/2025 COT - LCPL - Plumbing Intermediate Passed
10/23/2025 COT - LCEL - Electrical Intermediate Passed Passed final 10/23/25
10/29/2025 COT - LCEL - Electrical Above Ceiling Passed
11/05/2025 COT - FCON - Alarm - Final Passed
12/09/2025 COT - LCPL - Plumbing Final Passed Passed 12/9/25
12/09/2025 COT - LCME - Mechanical Final Passed Passed 12/9/25
12/09/2025 COT - LCEL - Electrical Final Passed Passed 12/9/25
12/09/2025 COT - FCON - Sprinkler - Final Passed
12/09/2025 COT - FCON - Fire - Final Passed
12/15/2025 COT - HCBU - TCO Passed oK for C of O.
12/15/2025 COT - LCBU - Building Final Passed oK for C of O.