Permit: TC-COM-0624-01176
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6001 E SPEEDWAY BL
Address NEW:
6001 E SPEEDWAY BL
Apply Date:
06/19/2024
Applicant:
Brad Davis
Description:
Interior tenant improvement to existing interior office area and customer restrooms. No changes to building size, site or occupancy are proposed.
Permit Reviews
Permit Number - TC-COM-0624-01176
Permit Status: Complete
Permit Description: Interior tenant improvement to existing interior office area and customer restrooms.
No changes to building size, site or occupancy are proposed.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/18/2024 | RESTAMP - COMMERCIAL v.1 | 09/19/2024 | APPROVED |
| 04/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/15/2025 | APPROVED |
| 06/20/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/26/2024 | REQUIRES RESUBMIT |
| 08/08/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/18/2024 | APPROVED |
| 05/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/05/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0624-01176
Permit Status: Complete
Permit Description: Interior tenant improvement to existing interior office area and customer restrooms.
No changes to building size, site or occupancy are proposed.
| Date | Description | Comments |
|---|---|---|
| 07/25/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 09/18/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 09/09/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01176
Permite Description: Interior tenant improvement to existing interior office area and customer restrooms.
No changes to building size, site or occupancy are proposed.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2024 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Walls only, including electric for restrooms.. |
| 04/11/2025 | COT - FCON - Alarm - Final | N/A | Not Applicable | |
| 04/11/2025 | COT - LCME - Mechanical Final | N/A | Partial Pass | AIR BALANCING REPORT IS REQUIRED. |
| 04/10/2025 | COT - LCPL - Plumbing Final | N/A | Partial Pass | WATER STERILIZATION REPORT IS REQUIRED. |
| 04/11/2025 | COT - FCON - Sprinkler - Final | N/A | Not Ready | Sprinkler needs to be evaluated by contactor, adjust/remove heads in west lobby and storeroom east of restrooms |
| 04/11/2025 | COT - FCON - Fire - Final | N/A | Not Ready | Sprinkler neeeds to be evaluated and work permitted |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01176
Permit Description: Interior tenant improvement to existing interior office area and customer restrooms.
No changes to building size, site or occupancy are proposed.
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2024 | COT - LCPL - Rough Soil | Passed | ||
| 11/13/2024 | COT - LCBU - Preslab | Passed | ||
| 12/13/2024 | COT - LCPL - Plumbing Intermediate | Passed | 12/13/24: plumbing rough in is complete for walls and above ceiling. | |
| 04/10/2025 | COT - LCEL - Electrical Final | Passed | ||
| 04/11/2025 | COT - LCBU - Framing | Passed | ||
| 04/11/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 04/11/2025 | COT - LCBU - Building Final | Passed | ||
| 04/11/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 04/11/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 04/30/2025 | COT - LCME - Mechanical Final | Passed | ||
| 04/30/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 05/05/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 05/05/2025 | COT - FCON - Fire - Final | Passed |