Permit: TC-COM-0624-01142
Permit Details
Apply Date:
06/13/2024
Applicant:
Austin Matson
Description:
INSTALLATION OF 99.55KWDC SOLAR PV SYSTEM, MOUNTED ON 3 NEW CANOPY STRUCTURES, (2) MAIN SERVICE COMBINATIONS OF SINGLE PHASE METER PACK SERVICES
Permit Reviews
Permit Number - TC-COM-0624-01142
Permit Status: Inspections
Permit Description: INSTALLATION OF 99.55KWDC SOLAR PV SYSTEM, MOUNTED ON 3 NEW CANOPY STRUCTURES, (2) MAIN SERVICE COMBINATIONS OF SINGLE PHASE METER PACK SERVICES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/13/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2024 | REQUIRES RESUBMIT |
09/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 09/25/2024 | APPROVED |
09/25/2024 | RESTAMP - COMMERCIAL v.1 | 09/26/2024 | APPROVED |
08/15/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/16/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0624-01142
Permit Status: Inspections
Permit Description: INSTALLATION OF 99.55KWDC SOLAR PV SYSTEM, MOUNTED ON 3 NEW CANOPY STRUCTURES, (2) MAIN SERVICE COMBINATIONS OF SINGLE PHASE METER PACK SERVICES
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
07/22/2024 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. |
07/22/2024 | SPECIAL INSPECTION FOR FABRICATORS IS REQUIRED |
07/22/2024 | SPECIAL INSPECTION FOR SOILS IS REQUIRED. |
07/22/2024 | SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0624-01142
Permite Description: INSTALLATION OF 99.55KWDC SOLAR PV SYSTEM, MOUNTED ON 3 NEW CANOPY STRUCTURES, (2) MAIN SERVICE COMBINATIONS OF SINGLE PHASE METER PACK SERVICES
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/07/2024 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Partial Pass | Efer for caisson footings for building #1 |
10/07/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Rebar grounding on steel columns for building #1. Ok to,place,concrete in,caisson footings. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0624-01142
Permit Description: INSTALLATION OF 99.55KWDC SOLAR PV SYSTEM, MOUNTED ON 3 NEW CANOPY STRUCTURES, (2) MAIN SERVICE COMBINATIONS OF SINGLE PHASE METER PACK SERVICES
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved underground electrical conduit from service panel equipment at Building 1 to the solar equipment at PV structure 1 and continued to PV structure 2 and Building 2. Underground electrical conduit also approved from PV structure 3 to service panel equipment at Building 3. All underground is completer, okay to backfill and for concrete/pavement placement |