Permit: TC-COM-0525-00987
Permit Details
Apply Date:
05/13/2025
Applicant:
Kelly Rehm
Description:
Parking Canopy - P2 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Permit Reviews
Permit Number - TC-COM-0525-00987
Permit Status: Complete
Permit Description: Parking Canopy - P2 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/10/2025 | APPROVED |
| 06/13/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/16/2025 | APPROVED |
| 12/09/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/12/2025 | APPROVED |
| 06/11/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/12/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0525-00987
Permit Status: Complete
Permit Description: Parking Canopy - P2 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
| Date | Description | Comments |
|---|---|---|
| 05/13/2025 | SPECIAL INSPECTION OF COLD-FORMED STEEL FRAMING IS REQUIRED | |
| 05/13/2025 | SPECIAL INSPECTION OF FABRICATORS IS REQUIRED | |
| 06/16/2025 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
| 05/13/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/13/2025 | SPECIAL INSPECTION OF STRUCTURAL STEEL IS REQUIRED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00987
Permite Description: Parking Canopy - P2 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | BULD - Electrical Clearance | N/A | Not Applicable | one meter sent on another permit. |
| 12/16/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Rapid shut down signage shall be provided. |
| 12/16/2025 | ENGR Engineering Final | N/A | Not Ready | 12/16/25 Concrete Pier at the north end is finished below grade in landscaped parking island. Not to plan. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00987
Permit Description: Parking Canopy - P2 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 12/16/2025 | COT - LCBU - Building Final | Passed | All work per approved plans. | |
| 12/16/2025 | COT - LCEL - Electrical Final | Passed | per approved plans | |
| 12/16/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 12/17/2025 | COT - FCON - Fire - Final | Passed | ||
| 01/22/2026 | ENGR Engineering Final | Passed |