Permit: TC-COM-0524-00913
Permit Details
Apply Date:
05/13/2024
Applicant:
Andrew Venne
Description:
Interior remodel
Permit Reviews
Permit Number - TC-COM-0524-00913
Permit Status: Complete
Permit Description: Interior remodel
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/07/2025 | REQUIRES RESUBMIT |
01/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/23/2025 | APPROVED |
09/20/2024 | RESTAMP - COMMERCIAL v.1 | 09/24/2024 | APPROVED |
01/16/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/17/2025 | APPROVED |
12/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/31/2024 | APPROVED |
09/19/2024 | COMMERCIAL REVIEW - FULL v.5 | 09/20/2024 | APPROVED |
07/08/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/02/2024 | REQUIRES RESUBMIT |
01/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 01/09/2025 | APPROVED |
05/16/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/27/2024 | REQUIRES RESUBMIT |
09/12/2024 | COMMERCIAL REVIEW - FULL v.4 | 09/18/2024 | REQUIRES RESUBMIT |
09/09/2024 | COMMERCIAL REVIEW - FULL v.3 | 09/12/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0524-00913
Permit Status: Complete
Permit Description: Interior remodel
Date | Description | Comments |
---|---|---|
09/16/2024 | AIR BALANCING REPORT IS REQUIRED. | |
05/16/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
09/16/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
09/16/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
09/16/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
09/16/2024 | Post-Installed Anchor Inspection Report is required. | |
09/19/2024 | SPECIAL INSPECTION FOR Intumescent Coating IS REQUIRED | |
09/16/2024 | SPECIAL INSPECTION FOR Structural Steel IS REQUIRED | |
09/16/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0524-00913
Permite Description: Interior remodel
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/18/2024 | COT - HCME - Mechanical Final | N/A | Not Ready | Contractor cancelled. |
12/18/2024 | COT - HCPL - Gas Final | N/A | Not Ready | Contractor cancelled. |
12/18/2024 | COT - HCPL - Plumbing Final | N/A | Not Ready | Contractor cancelled. |
COT - FCON - Hood System - Final | N/A | Not Ready | Called in for a smoke test. Needs to contact Mechanical Inspector. | |
COT - FCON - Fire - Final | N/A | Not Ready | Tested all new devices for Fire Alarm minus the Kitchen Hood System. Will need to add or replace amp for speaker strobes and test kitchen hood system. | |
12/31/2024 | COT - FCON - Alarm - Final | N/A | Partial Pass | Tested all new devices. Will need to add or replace amp for speaker strobes. |
12/31/2024 | COT - HCME - Kitchen Hood | N/A | Not Ready | Contractor cancelled, will reschedule for 2 January. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0524-00913
Permit Description: Interior remodel
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
10/17/2024 | COT - HCEL - Electrical Above Ceiling | Passed | New canned lighting for mezzanine. | |
10/17/2024 | COT - HCBU - Framing | Passed | OK to insulate and cover walls and progress areas. | |
10/17/2024 | COT - HCBU - Building Above Ceiling | Passed | Ok to set ceiling grids in progress areas. | |
10/28/2024 | ENGR Engineering Final | Passed | ||
10/28/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
10/28/2024 | COT - HCPL - Gas Pressure Test | Passed | Submit for gas clearance. | |
11/05/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
11/05/2024 | COT - BULD - SWG Clearance | Passed | No clearance required. Commercial meter has been installed. | |
11/05/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
11/05/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
11/05/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
12/18/2024 | COT - HCEL - Electrical Final | Passed | ||
12/31/2024 | COT - FCON - Sprinkler - Final | Passed | ||
01/03/2025 | COT - HCME - Mechanical Final | Passed | ||
01/03/2025 | COT - HCPL - Gas Final | Passed | ||
01/03/2025 | COT - HCPL - Plumbing Final | Passed | ||
01/13/2025 | COT - FCON - Hood System - Final | Passed | ||
01/13/2025 | COT - FCON - Fire - Final | Passed | ||
01/13/2025 | COT - FCON - Alarm - Final | Passed | ||
01/13/2025 | COT - HCBU - Building Final | Passed | ||
01/13/2025 | COT - HCME - Kitchen Hood | Passed | Ansul system has been recharged. |