Permit: TC-COM-0524-00872
Permit Details
Apply Date:
05/06/2024
Applicant:
Jason Razo
Description:
Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Permit Reviews
Permit Number - TC-COM-0524-00872
Permit Status: Inspections
Permit Description: Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/10/2024 | RESTAMP - COMMERCIAL v.1 | 09/11/2024 | APPROVED |
05/09/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/12/2024 | REQUIRES RESUBMIT |
08/07/2024 | COMMERCIAL REVIEW - FULL v.3 | 09/10/2024 | APPROVED |
07/02/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/06/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0524-00872
Permit Status: Inspections
Permit Description: Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
06/12/2024 | This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit. |
08/06/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0524-00872
Permit Status: Inspections
Permit Description: Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Date | Description | Comments |
---|---|---|
05/09/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
08/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/12/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0524-00872
Permite Description: Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2024 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 11/7/24: electrical intermediate at first floor bathrooms passed ok to proceed, electrical at first floor Baptistry passed ok to proceed, electrical in wall at changing rooms passed ok to proceed. |
11/07/2024 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 11/7/24: plumbing intermediate at bathrooms passed, plumbing in wall at baptistry passed, |
11/07/2024 | COT - LCBU - Framing | N/A | Partial Pass | 11/7/24: framing at first floor bathrooms and baptistry passed. Pending second floor and changing rooms. |
11/07/2024 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | 11/7/24: revision required for changes being made to first floor bathroom. Baptistry passed |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0524-00872
Permit Description: Tenant improvement for an existing church sanctuary. The area of improvement is 1,000 sf of new interior baptistry, changing rooms, and restroom to be located at the existing worship platform and upper-level mezzanine.
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/30/2024 | COT - HCBU - Preslab | Passed | Backstage sanctuary trench has been backfilled and compacted. Dowels are installed in existing concrete slab for pour back of trench cut out. Okay to proceed with bathroom and backstage concrete pour back. | |
09/30/2024 | COT - LCPL - Rough Soil | Passed | 9/30/24: full pass on backstage sanctuary underground plumbing and restroom underground plumbing. All are under a water test with no leaks. Okay to complete backfill and compaction, then pour back concrete slab. |