Permit: TC-COM-0523-01251
Permit Details
Apply Date:
05/10/2023
Applicant:
Kelly Rehm
Description:
The Camp Lowell Offices is a 22.5 kW DC grid tied PV system 45 Silfab 500W modules w/ 1 grid-tied inverter Modules go on one custom steel structure in the parking lot. The structure is designed for 75 modules; **only 45 modules are installed on this permit and are assigned to the electrical service of 3075 N Swan Rd (meter 151515725). The remaining 30 modules will be installed under a separate permit that references this permit.
Permit Reviews
Permit Number - TC-COM-0523-01251
Permit Status: Complete
Permit Description: The Camp Lowell Offices is a 22.5 kW DC grid tied PV system
45 Silfab 500W modules w/ 1 grid-tied inverter
Modules go on one custom steel structure in the parking lot. The structure is designed for 75 modules; **only 45 modules are installed on this permit and are assigned to the electrical service of 3075 N Swan Rd (meter 151515725). The remaining 30 modules will be installed under a separate permit that references this permit.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/19/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/16/2023 | REQUIRES RESUBMIT |
| 05/12/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/12/2023 | REQUIRES RESUBMIT |
| 07/21/2023 | RESTAMP - COMMERCIAL v.1 | 07/24/2023 | APPROVED |
| 08/17/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/29/2023 | APPROVED |
| 06/28/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/21/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0523-01251
Permit Status: Complete
Permit Description: The Camp Lowell Offices is a 22.5 kW DC grid tied PV system
45 Silfab 500W modules w/ 1 grid-tied inverter
Modules go on one custom steel structure in the parking lot. The structure is designed for 75 modules; **only 45 modules are installed on this permit and are assigned to the electrical service of 3075 N Swan Rd (meter 151515725). The remaining 30 modules will be installed under a separate permit that references this permit.
| Date | Description | Comments |
|---|---|---|
| 06/15/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 07/24/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 06/15/2023 | SUBMISSION OF SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS REPORT IS REQUIRED. | |
| 06/15/2023 | SUBMISSION OF SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01251
Permite Description: The Camp Lowell Offices is a 22.5 kW DC grid tied PV system
45 Silfab 500W modules w/ 1 grid-tied inverter
Modules go on one custom steel structure in the parking lot. The structure is designed for 75 modules; **only 45 modules are installed on this permit and are assigned to the electrical service of 3075 N Swan Rd (meter 151515725). The remaining 30 modules will be installed under a separate permit that references this permit.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/04/2023 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for line-side tap, DGL Clearance was called into TEP at 10:10am (meter #151515725) |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01251
Permit Description: The Camp Lowell Offices is a 22.5 kW DC grid tied PV system
45 Silfab 500W modules w/ 1 grid-tied inverter
Modules go on one custom steel structure in the parking lot. The structure is designed for 75 modules; **only 45 modules are installed on this permit and are assigned to the electrical service of 3075 N Swan Rd (meter 151515725). The remaining 30 modules will be installed under a separate permit that references this permit.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/01/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Approved 3 pier foundations, okay for concrete placement | |
| 08/07/2023 | COT - LCBU - Framing | Passed | ||
| 08/17/2023 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved all underground PV and secondary conduits from the service panel and PV equipment to the Canopy, okay to backfill progress areas | |
| 08/24/2023 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 08/24/2023 | BULD - Electrical Clearance | Passed | Approved, DGC/DGL Clearance to TEP is required for the solar meter (meter #151515725) | |
| 08/24/2023 | COT - LCBU - Building Final | Passed | ||
| 08/28/2023 | COT - LCEL - Electrical Final | Passed | ||
| 08/28/2023 | COT - CSOL - Electrical Intermediate Solar Project | Passed |