Permit: TC-COM-0425-00817
Permit Details
Apply Date:
04/23/2025
Applicant:
Kelly Rehm
Description:
Roof Mounted PV System - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Permit Reviews
Permit Number - TC-COM-0425-00817
Permit Status: Complete
Permit Description: Roof Mounted PV System - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/24/2025 | COMMERCIAL REVIEW - FULL v.1 | 05/19/2025 | APPROVED |
| 05/19/2025 | RESTAMP - COMMERCIAL v.1 | 05/20/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00817
Permite Description: Roof Mounted PV System - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Rapid shut down signage shall be provided. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00817
Permit Description: Roof Mounted PV System - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2025 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 12/16/2025 | COT - CSOL - Electrical Final Solar Project | Passed | All work per approved plans. | |
| 12/16/2025 | COT - LCBU - Building Final | Passed | All work per approved plans. | |
| 12/16/2025 | COT - LCEL - Electrical Final | Passed | All work per approved plans. | |
| 12/16/2025 | ENGR Engineering Final | Passed | ||
| 12/16/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 12/16/2025 | COT - CSOL - Electrical Intermediate Solar Project | Passed | All work per approved plans. | |
| 12/16/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 12/16/2025 | BULD - Electrical Clearance | Passed | DGC TEP |
|
| 12/17/2025 | COT - FCON - Fire - Final | Passed |