Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
7150 E SPEEDWAY BL
Apply Date:
04/10/2024
Applicant:
Dave Nanney
Description:
New Walmart Fuel Station

Permit Reviews

Permit Number - TC-COM-0424-00648
Permit Status: Complete
Permit Description: New Walmart Fuel Station
Start Date Submittal Complete Date Status  
07/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 07/21/2025 REQUIRES RESUBMIT Review Details
01/06/2025 COMMERCIAL REVIEW - FULL v.8 01/07/2025 APPROVED Review Details
07/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 07/24/2025 APPROVED Review Details
08/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 08/14/2025 APPROVED Review Details
10/29/2024 COMMERCIAL REVIEW - FULL v.5 10/30/2024 REQUIRES RESUBMIT Review Details
07/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/25/2025 APPROVED Review Details
12/02/2024 COMMERCIAL REVIEW - FULL v.7 12/02/2024 REQUIRES RESUBMIT Review Details
03/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/25/2025 APPROVED Review Details
02/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/25/2025 APPROVED Review Details
07/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/18/2025 REQUIRES RESUBMIT Review Details
01/07/2025 RESTAMP - COMMERCIAL v.1 01/13/2025 APPROVED Review Details
09/12/2024 COMMERCIAL REVIEW - FULL v.3 09/12/2024 REQUIRES RESUBMIT Review Details
11/06/2024 COMMERCIAL REVIEW - FULL v.6 11/27/2024 REQUIRES RESUBMIT Review Details
08/12/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/12/2025 REQUIRES RESUBMIT Review Details
03/11/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/12/2025 REQUIRES RESUBMIT Review Details
06/13/2024 COMMERCIAL REVIEW - FULL v.2 07/16/2024 REQUIRES RESUBMIT Review Details
09/18/2024 COMMERCIAL REVIEW - FULL v.4 10/22/2024 REQUIRES RESUBMIT Review Details
04/11/2024 COMMERCIAL REVIEW - FULL v.1 05/13/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0424-00648
Permit Status: Complete
Permit Description: New Walmart Fuel Station
Date Description Comments
01/07/2025 AIR BALANCING REPORT IS REQUIRED.
01/07/2025 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/07/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/11/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
01/07/2025 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
01/07/2025 Masonry Inspection Report submittal review is required.
02/25/2025 Post-Installed Anchor Inspection Report is required.
01/07/2025 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/11/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
01/07/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
01/07/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
01/07/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
01/07/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0424-00648
Permite Description: New Walmart Fuel Station
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
03/11/2025 COT - HCEL - Electrical Intermediate N/A Not Ready Wanted UG electric, but not on permit.
03/27/2025 COT - HCBU - Roof Nailing N/A Partial Pass 3-27-25, roof nailing approved-Okay to dry in .
03/04/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass Footings for fuel canopy.
04/17/2025 COT - HCEL - Electrical Underground N/A Partial Pass 4-17-25, okay to backfill approximately 100' of 3" secondary electrical conduits on south side of building. Rough-in mechanical verified per plans-okay to continue with construction at progress areas.
04/25/2025 COT - HCEL - Outdoor Lighting N/A Partial Pass Light pole bases.
03/04/2025 COT - HCEL - Grounding/Bonding N/A Partial Pass Grounding at fuel canopy.
COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0424-00648
Permit Description: New Walmart Fuel Station
Total Completed Inspections - 28
Date Description Inspector Results Comments
03/11/2025 COT - HCPL - Rough Soil Passed
03/12/2025 COT - HCBU - Preslab Passed
03/24/2025 COT - HCBU - Framing Passed
03/26/2025 COT - HCPL - Sewer Passed
04/02/2025 COT - HCPL - Plumbing Intermediate Passed
04/02/2025 COT - HCEL - Electrical Intermediate Passed
04/03/2025 COT - HCBU - Roof Nailing Passed
04/15/2025 COT - HCPL - Yard Water Line Passed
04/17/2025 COT - HCME - Mechanical Above Ceiling Passed
04/25/2025 COT - HCBU - Excavation/Rebar/Zoning Passed Light pole bases.
04/30/2025 COT - HCEL - Electrical Underground Passed
05/16/2025 BULD - Electrical Clearance Passed Approved new 400A 3-phase service - ECO Clearance to TEP is required (Fuel Station location addressed as 7200 E Speedway Bl)
05/20/2025 COT - HCPL - Plumbing Roof Drains Passed
05/20/2025 COT - HCEL - Outdoor Lighting Passed
05/20/2025 COT - HCEL - Grounding/Bonding Passed
05/20/2025 COT - HCBU - Building Above Ceiling Passed
05/20/2025 COT - HCEL - Electrical Above Ceiling Passed
05/20/2025 COT - HCPL - Plumbing Above Ceiling Passed
05/20/2025 COT - HCPL - Plumbing Final Passed
05/20/2025 COT - BULD - SWG Clearance Passed SWG
05/20/2025 COT - HCME - Mechanical Intermediate Passed
06/03/2025 COT - HCME - Mechanical Final Passed
06/03/2025 COT - HCEL - Electrical Final Passed
06/03/2025 COT - HCBU - Building Final Passed
06/03/2025 TRSP - ROW - Final/Close-Out Passed
06/03/2025 ENGR Engineering Final Passed
06/03/2025 COT - HCBU - TCO Passed Level Four
07/08/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
TC-COM-0424-00648_WM SUP 1291-1001_63241125_CERT - SIGNED_V1.PDF DOCUMENTS VIEW
FUEL CENTER 1291 FINAL TAB_V1.PDF DOCUMENTS VIEW
TC-COM-0424-00648_WM SUP 1291-1001 FUEL STATION_63241125 CLOSE OUT SIGNED-2025-07-22_V2.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
0 - 4463057 TRUSS CALCS 3-20-2025_V2.PDF DOCUMENTS VIEW
STATEMENT OF SPECIAL INSPECTIONS-SIGNED-2025-02-20_V1.PDF DOCUMENTS VIEW
CONS-1291-1001 TUCSON AZ FUEL - CCD1 - COMPLETE SET_V7.PDF DOCUMENTS VIEW