Permit: TC-COM-0423-01140
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3100 E SPEEDWAY BL
Address NEW:
3100 E SPEEDWAY BL
Apply Date:
04/25/2023
Applicant:
Anthony Capps
Description:
Construct new drive through food service restaurant
Permit Reviews
Permit Number - TC-COM-0423-01140
Permit Status: Complete
Permit Description: Construct new drive through food service restaurant
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/30/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/02/2024 | APPROVED |
| 04/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/12/2024 | APPROVED |
| 08/01/2023 | COMMERCIAL REVIEW - FULL v.4 | 08/22/2023 | APPROVED |
| 05/01/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/01/2023 | REQUIRES RESUBMIT |
| 11/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/05/2023 | APPROVED |
| 06/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/14/2023 | REQUIRES RESUBMIT |
| 09/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/11/2024 | APPROVED |
| 07/10/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/20/2023 | REQUIRES RESUBMIT |
| 09/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/20/2024 | REQUIRES RESUBMIT |
| 08/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/21/2024 | REQUIRES RESUBMIT |
| 09/23/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/24/2024 | APPROVED |
| 08/22/2023 | RESTAMP - COMMERCIAL v.1 | 08/24/2023 | APPROVED |
| 11/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/22/2023 | REQUIRES RESUBMIT |
| 12/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2023 | APPROVED |
| 09/27/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/28/2023 | APPROVED |
| 07/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/05/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0423-01140
Permit Status: Complete
Permit Description: Construct new drive through food service restaurant
| Date | Description | Comments |
|---|---|---|
| 04/10/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 08/22/2023 | Prefabricated Canopies Designs must be submitted and approved prior to final. | |
| 04/10/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 04/10/2024 | Please submit a separate sign permit for an signs associated with this projet. | |
| 07/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 08/22/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 04/10/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01140
Permite Description: Construct new drive through food service restaurant
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| PDSD Heavy Commercial Building Division Pre-Construction Meeting | N/A | Requested | ||
| 10/19/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | All except South wall , which will have Ufer. |
| 11/21/2023 | COT - HCBU - Framing | N/A | Partial Pass | OK to sheet outside walls. |
| 12/07/2023 | COT - HCBU - Preslab | N/A | Partial Pass | Partial pass. Page S4.0. Detail 102 and 103 exterior wall footing at openings. At door entry, window and store front opening. Rebar per plan. Okay for concrete placement. 12/7/2023 |
| 04/02/2024 | COT - HCBU - TCO | N/A | Not Applicable | |
| 04/02/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01140
Permit Description: Construct new drive through food service restaurant
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
| 11/07/2023 | COT - HCPL - Backwater Valve | Passed | Okay to backfill. Shading required. 11/7/2023 | |
| 11/20/2023 | COT - HCEL - Grounding/Bonding | Passed | Ground wire and bond clamps are installed on all 5 light pole rebar cages. Okay to pour concrete for light pole bases. | |
| 11/20/2023 | COT - HCEL - Electrical Underground | Passed | 11/20/23: Ground wire and bond clamps are installed on all 5 light pole rebar cages. Okay to pour concrete for light pole bases. | |
| 11/21/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 12/05/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 12/05/2023 | COT - HCBU - Framing | Passed | ||
| 12/18/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
| 01/16/2024 | COT - HCBU - Roof Nailing | Passed | ||
| 01/22/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 01/22/2024 | COT - HCBU - Preslab | Passed | ||
| 01/22/2024 | COT - HCPL - Rough Soil | Passed | ||
| 01/22/2024 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 02/16/2024 | COT - HCEL - Electrical Progress | Passed | Electrical service entrance and sub-panels are installed, with 4" conduit ran from gutter in ceiling to sub-panel location. Will issue a ECO Clearance for TEP to energize service entrance. | |
| 03/20/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
| 03/20/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 03/20/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
| 03/20/2024 | COT - HCME - Mechanical Final | Passed | ||
| 03/20/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 03/20/2024 | COT - HCME - Venting | Passed | ||
| 03/20/2024 | COT - HCPL - Gas Final | Passed | ||
| 03/20/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
| 03/20/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 03/20/2024 | COT - HCPL - Sewer | Passed | ||
| 03/20/2024 | COT - HCPL - Yard Water Line | Passed | ||
| 04/05/2024 | BULD - Electrical Clearance | Passed | ||
| 04/22/2024 | COT - HCBU - Building Final | Passed | 4/22/24: Exterior portion of the shell building is complete. Okay to issue Certificate of Completion for this permit. TI build out to be performed under separate permit. | |
| 04/22/2024 | COT - HCEL - Electrical Final | Passed | 4/22/24: Electrical panels are installed and properly labeled for the exterior portion of the shell building. Okay to issue Certificate of Completion for this permit. TI build out to be performed under separate permit. | |
| 08/07/2024 | COT - FCON - Fire - Final | Passed | ||
| 04/22/2024 | ENGR Engineering Final | Passed | ||
| 04/22/2024 | TRSP - ROW - Final/Close-Out | Passed |