Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
04/11/2023
Applicant:
Corky Poster
Description:
EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.

Permit Reviews

Permit Number - TC-COM-0423-01033
Permit Status: Issued
Permit Description: EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Start Date Submittal Complete Date Status  
06/27/2023 COMMERCIAL REVIEW - FULL v.2 07/03/2023 APPROVED Review Details
04/27/2023 COMMERCIAL REVIEW - FULL v.1 05/30/2023 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0423-01033
Permit Status: Issued
Permit Description: EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Activity Conditions - 14
Date Name
06/16/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
06/16/2023 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
06/16/2023 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
06/16/2023 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/16/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/16/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/16/2023 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
06/16/2023 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
06/16/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
06/16/2023 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
06/16/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
06/16/2023 WATER STERILIZATION REPORT IS REQUIRED.
06/26/2023 Prior to project being finalized applicant must provide new water easement recordation information
07/28/2023 Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt

Conditions

Permit Number - TC-COM-0423-01033
Permit Status: Issued
Permit Description: EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Date Description Comments
04/27/2023 Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512
04/27/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
06/16/2023 NESHAP Permit is required. (Utilized with commercial demolition permits)

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0423-01033
Permite Description: EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
01/29/2024 COT - BULD - SWG Clearance N/A Canceled 1/29/24: Not ready for SWG Clearance at this time.
07/11/2024 COT - HCPL - Plumbing Intermediate N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
07/11/2024 COT - HCME - Mechanical Intermediate N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
07/11/2024 COT - HCEL - Electrical Intermediate N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
07/11/2024 COT - HCEL - Electrical Progress N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
07/11/2024 COT - HCEL - Electrical Above Ceiling N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
08/09/2024 COT - HCPL - Sewer N/A Partial Pass
08/15/2024 COT - HCPL - Yard Water Line N/A Partial Pass Partial pass for main waterline north of building 10 south of building nine running east and west no connection to meter at this time
07/11/2024 COT - HCEL - Electrical Underground N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
07/11/2024 COT - HCEL - Grounding/Bonding N/A Re-inspection required 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: seal all penetrations through vapor barrier, seal all penetrations through top plate, secure electrical wiring 8"from box, nail plates missing throughout. Per previous Notes. STOPPED INSPECTION MORE ITEMS MAY BE ADDED

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0423-01033
Permit Description: EXISTING BLDG 10, REHAB, 5517 SF, 5 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Completed Inspections - 9
Date Description Inspector Results Comments
01/29/2024 COT - LCPL - Rough Soil Passed Underground plumbing for Building #10 is complete and holding a water test in each unit. Okay to shade pipes and backfill trenches for slab pour back.
07/01/2024 COT - LCBU - Preslab Passed
07/11/2024 COT - HCPL - Plumbing Intermediate Passed 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: corrections made ok to proceed.
07/11/2024 COT - HCME - Mechanical Intermediate Passed 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: corrections made ok to proceed.
07/11/2024 COT - HCEL - Electrical Intermediate Passed 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: corrections made ok to proceed.
07/11/2024 COT - HCEL - Electrical Progress Passed 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: corrections made ok to proceed.
07/11/2024 COT - HCEL - Electrical Above Ceiling Passed 7/1/24: M.E.P inspection failed, secure electrical wiring 8" from receptacles, DVW not under test, Domestic water not under test, seal all penetrations through vapor barrier and top plates throughout, nail plates missing throughout, exhaust fans not wired in, grounding at electrical panels must be installed correctly, low voltage boxes not roughed in, properly terminate electrical wiring in boxes (sheathing must extend 1/2" into box), damaged wiring must be replaced, knockouts at panel must be sealed, Condensate drain must be appropriately supported midway in walls, fire blocking required at soffit. (All units except commercial unit.
7/11/24: corrections made ok to proceed.
11/06/2024 COT - HCEL - Grounding/Bonding Passed
11/12/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. Building #10.
10-113,10-112,10-111,10-110,10-109,10-100.
11/12/2024

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW