Permit: TC-COM-0325-00628
Permit Details
Apply Date:
03/28/2025
Applicant:
Charles Pifer
Description:
CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019. REV1: updated electrical to match separate solar permit submittal.
Permit Reviews
Permit Number - TC-COM-0325-00628
Permit Status: Issued
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
REV1: updated electrical to match separate solar permit submittal.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/03/2025 | HAST - COMMERCIAL NEW ADD/ALT FAST TRACK v.1 | 05/05/2025 | REQUIRES RESUBMIT |
| 05/08/2025 | HAST - COMMERCIAL NEW ADD/ALT FAST TRACK v.2 | 05/12/2025 | APPROVED |
| 07/28/2026 | SPECIAL INSPECTION REVIEW v.2 | 07/30/2026 | APPROVED |
| 02/09/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 02/09/2026 | REQUIRES RESUBMIT |
| 04/14/2026 | COMMERCIAL REVIEW - FULL REVISION v.3 | 04/16/2026 | APPROVED |
| 02/12/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 03/09/2026 | REQUIRES RESUBMIT |
| 07/22/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/22/2026 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0325-00628
Permit Status: Issued
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
REV1: updated electrical to match separate solar permit submittal.
| Date | Description | Comments |
|---|---|---|
| 04/18/2025 | SPECIAL INSPECTION OF CONCRETE CONSTRUCTION REQUIRED. | |
| 05/12/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 04/03/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 06/24/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 04/18/2025 | SPECIAL INSPECTION OF STEEL CONSTRUCTION IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00628
Permite Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
REV1: updated electrical to match separate solar permit submittal.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Courtyard |
| 11/18/2025 | COT - LCME - Mechanical Final | N/A | Not Applicable | |
| 11/18/2025 | COT - LCPL - Plumbing Final | N/A | Not Applicable | |
| 12/11/2025 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0325-00628
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
REV1: updated electrical to match separate solar permit submittal.
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/17/2025 | PDSD Building Division Pre-Construction Meeting | Passed | ||
| 10/17/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Discussed inspections required for the scope of work. will add appropriate inspections to DP | |
| 10/17/2025 | COT - BULD - SWG Clearance | Passed | ||
| 10/29/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 11/12/2025 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | Passed | ||
| 11/12/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 11/18/2025 | COT - LCBU - Preslab | Passed | ||
| 12/11/2025 | COT - LCBU - Framing | Passed | ||
| 04/08/2026 | COT - LCEL - Electrical Intermediate | Passed | ||
| 04/08/2026 | COT - LCEL - Grounding/Bonding | Passed | ||
| 04/08/2026 | COT - LCEL - Outdoor Lighting | Passed | ||
| 07/09/2026 | BULD - Electrical Clearance | Passed | ||
| 07/13/2026 | PDSD Building Division SIte Consultation | Passed |