Permit: TC-COM-0324-00397
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
9355 E VALENCIA RD
Address NEW:
9355 E VALENCIA RD
Apply Date:
03/01/2024
Applicant:
Jeff Lowy
Description:
New Tucson Water Well Site
Permit Reviews
Permit Number - TC-COM-0324-00397
Permit Status: Inspections
Permit Description: New Tucson Water Well Site
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/06/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/25/2024 | REQUIRES RESUBMIT |
| 04/15/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/15/2024 | APPROVED |
| 05/15/2024 | RESTAMP - COMMERCIAL v.1 | 05/20/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0324-00397
Permit Status: Inspections
Permit Description: New Tucson Water Well Site
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/19/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 03/19/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 03/19/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Conditions
Permit Number - TC-COM-0324-00397
Permit Status: Inspections
Permit Description: New Tucson Water Well Site
| Date | Description | Comments |
|---|---|---|
| 03/06/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/22/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) TD-DEV-0323-00188 permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0324-00397
Permite Description: New Tucson Water Well Site
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2024 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | 7/25/24: not ready tank not grounded at this time |
| 07/25/2024 | COT - LCBU - Preslab | N/A | Partial Pass | 7/25/24: okay to pour air compressor pad |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0324-00397
Permit Description: New Tucson Water Well Site
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2024 | COT - LCEL - Electrical Progress | Passed | ||
| 09/19/2024 | COT - LCEL - Electrical Underground | Passed | 9/19/24: intrusion and air compressor | |
| 09/19/2024 | COT - LCEL - Grounding/Bonding | Passed | 9/19/24: grounding and bonding for pressure tank and control building good to cover. | |
| 10/02/2024 | BULD - Electrical Clearance | Passed | Okay to energize. ECO Clearance issued for 9355 E Valencia Rd. | |
| 01/08/2025 | COT - LCBU - Preslab | Passed | ||
| 01/08/2025 | COT - LCBU - Building Final | Passed | Control building is complete. Electrical panels, meter box, and disconnects are installed and fully functional. Okay to issue Certificate of Completion. | |
| 01/08/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/08/2025 | COT - LCBU - Masonry Pregrout | Passed | ||
| 01/08/2025 | COT - LCPL - Plumbing Final | Passed | Control building is complete. Electrical panels, meter box, and disconnects are installed and fully functional. Okay to issue Certificate of Completion. | |
| 01/08/2025 | COT - LCME - Mechanical Final | Passed | Control building is complete. Electrical panels, meter box, and disconnects are installed and fully functional. Okay to issue Certificate of Completion. | |
| 01/08/2025 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 01/08/2025 | COT - LCEL - Electrical Final | Passed | Control building is complete. Electrical panels, meter box, and disconnects are installed and fully functional. Okay to issue Certificate of Completion. | |
| 01/08/2025 | COT - LCEL - Electrical Intermediate | Passed | 1/8/25: Grounding of intrusion metal boxes is completed per plan specifications. | |
| 01/08/2025 | COT - LCEL - Outdoor Lighting | Passed | Control building is complete. Electrical panels, meter box, and disconnects are installed and fully functional. Okay to issue Certificate of Completion. |