Permit: TC-COM-0226-00166
Permit Details
Apply Date:
02/04/2026
Applicant:
Joe Alitiem
Description:
Install a parking structure solar array. SCOPE OF WORK SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC PTC : 84 X 502.2W = 42.18 KW DC AC SIZE: 60.0 KW AC 84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES (01) SOLIS S5-GC60K-LV-US (208V) INVERTER. Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
Permit Reviews
Permit Number - TC-COM-0226-00166
Permit Status: Approved
Permit Description: Install a parking structure solar array.
SCOPE OF WORK
SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC
PTC : 84 X 502.2W = 42.18 KW DC
AC SIZE: 60.0 KW AC
84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES
(01) SOLIS S5-GC60K-LV-US (208V) INVERTER.
Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/26/2026 | ADMINISTRATIVE v.2 | 05/26/2026 | APPROVED |
| 05/08/2026 | COMMERCIAL REVIEW - FULL v.4 | 05/13/2026 | APPROVED |
| 07/14/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | N/A | IN REVIEW |
| 05/26/2026 | SPECIAL INSPECTION REVIEW v.1 | 05/26/2026 | REQUIRES RESUBMIT |
| 03/13/2026 | COMMERCIAL REVIEW - FULL v.2 | 04/03/2026 | REQUIRES RESUBMIT |
| 02/04/2026 | COMMERCIAL REVIEW - FULL v.1 | 03/03/2026 | REQUIRES RESUBMIT |
| 04/24/2026 | COMMERCIAL REVIEW - FULL v.3 | 05/07/2026 | REQUIRES RESUBMIT |
| 05/13/2026 | ADMINISTRATIVE v.1 | 05/13/2026 | REQUIRES RESUBMIT |
| 07/14/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/16/2026 | APPROVED |
| 05/26/2026 | SPECIAL INSPECTION REVIEW v.2 | 05/27/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0226-00166
Permit Status: Approved
Permit Description: Install a parking structure solar array.
SCOPE OF WORK
SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC
PTC : 84 X 502.2W = 42.18 KW DC
AC SIZE: 60.0 KW AC
84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES
(01) SOLIS S5-GC60K-LV-US (208V) INVERTER.
Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 02/27/2026 | SPECIAL INSPECTION INSPECTION OF CONCRETE CONSTRUCTION IS REQUIRED. |
| 02/27/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 02/27/2026 | SPECIAL INSPECTION INSPECTION OF STRUCTURAL STEEL IS REQUIRED. |
Conditions
Permit Number - TC-COM-0226-00166
Permit Status: Approved
Permit Description: Install a parking structure solar array.
SCOPE OF WORK
SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC
PTC : 84 X 502.2W = 42.18 KW DC
AC SIZE: 60.0 KW AC
84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES
(01) SOLIS S5-GC60K-LV-US (208V) INVERTER.
Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
| Date | Description | Comments |
|---|---|---|
| 02/04/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/27/2026 | SPECIAL INSPECTION INSPECTION OF SOILS IS REQUIRED. | |
| 02/27/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Completed Inspections
Permit Status: Approved
Permit Number: TC-COM-0226-00166
Permit Description: Install a parking structure solar array.
SCOPE OF WORK
SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC
PTC : 84 X 502.2W = 42.18 KW DC
AC SIZE: 60.0 KW AC
84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES
(01) SOLIS S5-GC60K-LV-US (208V) INVERTER.
Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2026 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 07/14/2026 | BULD - Electrical Clearance | Passed | 7.14.26 TEP CLEARANCE: DGC |
|
| 07/14/2026 | COT - FCON - Fire - Final | Passed | ||
| 07/14/2026 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 07/14/2026 | COT - LCBU - Building Final | Passed | ||
| 07/14/2026 | COT - LCEL - Electrical Final | Passed | ||
| 07/14/2026 | ENGR Engineering Final | Passed | ||
| 07/13/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 07/14/2026 | COT - CSOL - Electrical Underground Solar Project | Passed |