Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Commercial Building
Address:
2936 N STONE AV
Address NEW:
2936 N STONE AV
Apply Date:
02/11/2025
Applicant:
Jeff Shoemaker
Description:
Replacing existing PV system with all new PV, roof mounted 17 panel, 6.715kW

Permit Reviews

Permit Number - TC-COM-0225-00273
Permit Status: Inspections complete
Permit Description: Replacing existing PV system with all new PV, roof mounted 17 panel, 6.715kW
Start Date Submittal Complete Date Status  
06/30/2025 COMMERCIAL REVIEW - FULL v.2 06/30/2025 REQUIRES RESUBMIT Review Details
02/11/2025 COMMERCIAL REVIEW - FULL v.1 03/12/2025 REQUIRES RESUBMIT Review Details
07/01/2025 COMMERCIAL REVIEW - FULL v.3 07/21/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0225-00273
Permit Status: Inspections complete
Permit Description: Replacing existing PV system with all new PV, roof mounted 17 panel, 6.715kW
Date Description Comments
07/18/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0225-00273
Permite Description: Replacing existing PV system with all new PV, roof mounted 17 panel, 6.715kW
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/02/2025 COT - FCON - Fire - Final N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0225-00273
Permit Description: Replacing existing PV system with all new PV, roof mounted 17 panel, 6.715kW
Total Completed Inspections - 6
Date Description Inspector Results Comments
08/27/2025 COT - CSOL - Electrical Underground Solar Project Passed Approved electrical conduit from panel to solar equipment,okay to backfill progress areas
09/02/2025 COT - CSOL - Electrical Final Solar Project Passed
09/02/2025 COT - LCBU - Building Final Passed
09/02/2025 COT - CSOL - Electrical Intermediate Solar Project Passed
09/02/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
09/02/2025 BULD - Electrical Clearance Passed Approved solar - DGC Clearance to TEP is required for the solar meter

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-JOSEPH PLANS R2_V3.PDF DOCUMENTS VIEW
JOSEPH STRUCTURAL CALCULATIONS_V2.PDF DOCUMENTS VIEW