Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
02/02/2024
Applicant:
Adam Abreu
Description:
Tenant Improvement for European Wax Center

Permit Reviews

Permit Number - TC-COM-0224-00231
Permit Status: Complete
Permit Description: Tenant Improvement for European Wax Center
Start Date Submittal Complete Date Status  
04/09/2024 COMMERCIAL REVIEW - LIMITED v.2 04/26/2024 REQUIRES RESUBMIT Review Details
05/09/2024 RESTAMP - COMMERCIAL v.1 05/13/2024 APPROVED Review Details
04/26/2024 COMMERCIAL REVIEW - LIMITED v.3 05/09/2024 APPROVED Review Details
02/02/2024 COMMERCIAL REVIEW - LIMITED v.1 02/22/2024 REQUIRES RESUBMIT Review Details
08/14/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/15/2024 APPROVED Review Details
09/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/16/2024 APPROVED Review Details
08/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/16/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0224-00231
Permit Status: Complete
Permit Description: Tenant Improvement for European Wax Center
Date Description Comments
04/23/2024 AIR BALANCING REPORT IS REQUIRED.
02/02/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
02/21/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0224-00231
Permite Description: Tenant Improvement for European Wax Center
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
05/31/2024 COT - LCBU - Preslab N/A Re-inspection required 5/31/24: Preslab reinforcement not per plan
06/18/2024 COT - LCBU - Framing N/A Not Ready 6/13/24: stud bracing missing throughout.
6/18/24:not ready
06/13/2024 COT - LCEL - Electrical Intermediate N/A Partial Pass 6/13/24: electrical in wall per plan ok to proceed.
06/13/2024 COT - LCPL - Plumbing Intermediate N/A Partial Pass 6/13/24: plumbing in walls passed ok to proceed.
07/25/2024 COT - LCEL - Electrical Above Ceiling N/A Partial Pass 7/23/24: Exit sign missing at new door opening, properly support all MC cable off grid, properly support all light fixtures, properly label all j-boxes, install all light fixtures to verify proper support of fixture and MC cable.
7/25/24: Exit sign missing at new door opening. All MC cable has been properly supported and j-box have been labeled. Ok to lay ceiling tiles.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0224-00231
Permit Description: Tenant Improvement for European Wax Center
Total Completed Inspections - 14
Date Description Inspector Results Comments
05/29/2024 COT - LCPL - Rough Soil Passed 4/29/24: plumbing underground per plans and under test ok to backfill. Shading required
06/04/2024 COT - LCBU - Preslab Passed 5/31/24: Preslab reinforcement not per plan
6/4/24: RFI provided for Preslab reinforcement. Passed
06/18/2024 COT - LCBU - Framing Passed 6/13/24: stud bracing missing throughout.
6/18/24:corrections made ok to proceed.
07/23/2024 COT - LCEL - Electrical Intermediate Passed
07/23/2024 COT - LCPL - Plumbing Intermediate Passed
07/25/2024 COT - LCME - Mechanical Intermediate Passed 6/13/24: dampers missing, seal all joints throughout.
6/18/24: mechanical intermediate passed. Pending above ceiling
7/23/24: properly support all diffusers with 2 12 gauge safety wires. Properly terminate supply and return at hallway,bathroom and storage.
7/25/24: corrections made ok to proceed.
07/25/2024 BULD - Electrical Clearance Passed 7/23/24: not ready
7/25/24: ECO TEP CLEARANCE for 4734 S LANDING WY UNIT 110.
08/12/2024 COT - BULD - SWG Clearance Passed
08/12/2024 COT - LCEL - Electrical Above Ceiling Passed
08/13/2024 COT - LCME - Mechanical Final Passed
08/13/2024 COT - LCEL - Electrical Final Passed
08/13/2024 COT - FCON - Fire - Final Passed
08/13/2024 COT - LCPL - Plumbing Final Passed
08/15/2024 COT - LCBU - Building Final Passed Grab bars need to be 36" to top of bar. Electrical panel needs to be printed labels. Pending both T&B and chlorination reports prior to final inspection. 8/12/2024
8/13/24: pending Air balance report and water sterilization report. Pending fire final. Pending RFI on new store front opening.
8/15/24: ok for CofO

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
2ND AIR BALL REPORT_V2.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
24H0338_1 TURNERRES 08 13 2024 1630-2024-08-14_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-EWC TUCSON PLAN CHECK CORRECTIONS 2 SET 04-23-2024_V3.PDF DOCUMENTS VIEW