Permit: TC-COM-0224-00231
Permit Details
Apply Date:
02/02/2024
Applicant:
Reynaldo Garcia
Description:
Tenant Improvement for European Wax Center
Permit Reviews
Permit Number - TC-COM-0224-00231
Permit Status: Complete
Permit Description: Tenant Improvement for European Wax Center
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 04/26/2024 | REQUIRES RESUBMIT |
05/09/2024 | RESTAMP - COMMERCIAL v.1 | 05/13/2024 | APPROVED |
04/26/2024 | COMMERCIAL REVIEW - LIMITED v.3 | 05/09/2024 | APPROVED |
02/02/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 02/22/2024 | REQUIRES RESUBMIT |
08/14/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/15/2024 | APPROVED |
09/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/16/2024 | APPROVED |
08/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/16/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0224-00231
Permit Status: Complete
Permit Description: Tenant Improvement for European Wax Center
Date | Description | Comments |
---|---|---|
04/23/2024 | AIR BALANCING REPORT IS REQUIRED. | |
02/02/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
02/21/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00231
Permite Description: Tenant Improvement for European Wax Center
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2024 | COT - LCBU - Preslab | N/A | Re-inspection required | 5/31/24: Preslab reinforcement not per plan |
06/18/2024 | COT - LCBU - Framing | N/A | Not Ready | 6/13/24: stud bracing missing throughout. 6/18/24:not ready |
06/13/2024 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 6/13/24: electrical in wall per plan ok to proceed. |
06/13/2024 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 6/13/24: plumbing in walls passed ok to proceed. |
07/25/2024 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 7/23/24: Exit sign missing at new door opening, properly support all MC cable off grid, properly support all light fixtures, properly label all j-boxes, install all light fixtures to verify proper support of fixture and MC cable. 7/25/24: Exit sign missing at new door opening. All MC cable has been properly supported and j-box have been labeled. Ok to lay ceiling tiles. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00231
Permit Description: Tenant Improvement for European Wax Center
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/29/2024 | COT - LCPL - Rough Soil | Passed | 4/29/24: plumbing underground per plans and under test ok to backfill. Shading required | |
06/04/2024 | COT - LCBU - Preslab | Passed | 5/31/24: Preslab reinforcement not per plan 6/4/24: RFI provided for Preslab reinforcement. Passed |
|
06/18/2024 | COT - LCBU - Framing | Passed | 6/13/24: stud bracing missing throughout. 6/18/24:corrections made ok to proceed. |
|
07/23/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
07/23/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
07/25/2024 | COT - LCME - Mechanical Intermediate | Passed | 6/13/24: dampers missing, seal all joints throughout. 6/18/24: mechanical intermediate passed. Pending above ceiling 7/23/24: properly support all diffusers with 2 12 gauge safety wires. Properly terminate supply and return at hallway,bathroom and storage. 7/25/24: corrections made ok to proceed. |
|
07/25/2024 | BULD - Electrical Clearance | Passed | 7/23/24: not ready 7/25/24: ECO TEP CLEARANCE for 4734 S LANDING WY UNIT 110. |
|
08/12/2024 | COT - BULD - SWG Clearance | Passed | ||
08/12/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
08/13/2024 | COT - LCME - Mechanical Final | Passed | ||
08/13/2024 | COT - LCEL - Electrical Final | Passed | ||
08/13/2024 | COT - FCON - Fire - Final | Passed | ||
08/13/2024 | COT - LCPL - Plumbing Final | Passed | ||
08/15/2024 | COT - LCBU - Building Final | Passed | Grab bars need to be 36" to top of bar. Electrical panel needs to be printed labels. Pending both T&B and chlorination reports prior to final inspection. 8/12/2024 8/13/24: pending Air balance report and water sterilization report. Pending fire final. Pending RFI on new store front opening. 8/15/24: ok for CofO |