Inspection History Details
Inspection Status: Requested
Inspection History: COT - HCBU - Masonry Pregrout
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCBU - Masonry Pregrout | Requested | |||
| 10/27/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | ||
| 10/29/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | ||
| 11/03/2026 | COT - HCBU - Masonry Pregrout | Not Ready | ||
| 11/06/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | CNG Control building. 3rd lift at all perimeter walls approved. Corrections have been made per previous notes. Okay to grout all progress areas. 12’ cmu wall per key note 11 on page C200. 1st lift at Walls between both equipment pads CNG pad. North to south and heading east. Okay to grout all progress areas. Approved per detail 110 page S3.0 11/6/2026 |