Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
02/01/2023
Applicant:
Andrew Suby
Description:
Equipment replacement of an existing MRI Equipment with minor renovations of finishes within MRI Exam Room #3 within Tower #1 of the Banner University Medical Center Campus.

Permit Reviews

Permit Number - TC-COM-0223-00567
Permit Status: Issued
Permit Description: Equipment replacement of an existing MRI Equipment with minor renovations of finishes within MRI Exam Room #3 within Tower #1 of the Banner University Medical Center Campus.
Start Date Submittal Complete Date Status  
12/19/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/19/2023 APPROVED Review Details
07/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/17/2023 APPROVED Review Details
06/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/29/2023 APPROVED Review Details
02/10/2023 COMMERCIAL REVIEW - FULL v.1 03/06/2023 APPROVED Review Details
06/09/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/27/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0223-00567
Permit Status: Issued
Permit Description: Equipment replacement of an existing MRI Equipment with minor renovations of finishes within MRI Exam Room #3 within Tower #1 of the Banner University Medical Center Campus.
Date Description Comments
03/06/2023 Contractor's active Arizona Contractor's License number for specified scope of work required prior to issuance of permit.
05/24/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/23/2023 SPECIAL INSPECTION FOR MEDICAL GASES IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0223-00567
Permite Description: Equipment replacement of an existing MRI Equipment with minor renovations of finishes within MRI Exam Room #3 within Tower #1 of the Banner University Medical Center Campus.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
06/07/2023 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable
06/07/2023 COT - HCBU - Interior Shear Bracing N/A Not Applicable
06/07/2023 COT - HCME - Mechanical Final N/A Not Applicable
06/07/2023 COT - HCBU - Building Final N/A Not Ready
06/07/2023 COT - HCEL - Electrical Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0223-00567
Permit Description: Equipment replacement of an existing MRI Equipment with minor renovations of finishes within MRI Exam Room #3 within Tower #1 of the Banner University Medical Center Campus.
Total Completed Inspections - 13
Date Description Inspector Results Comments
04/21/2023 COT - HCBU - Building Progress Passed Ok to cover and repair walls
04/21/2023 COT - HCBU - Building Above Ceiling Passed Ok to set ceiling grid and place ceiling tiles.
06/05/2023 COT - FCON - Fire - Final Passed
06/05/2023 COT - FCON - Sprinkler - Final Passed
06/06/2023 COT - FCON - Alarm - Final Passed
06/07/2023 ENGR Engineering Final Passed
06/07/2023 COT - HCEL - Electrical Above Ceiling Passed
06/07/2023 COT - HCME - Mechanical Above Ceiling Passed
06/07/2023 COT - HCME - Mechanical Intermediate Passed
06/07/2023 COT - HCPL - Medical Gas/Final Passed med gas 12, may
06/07/2023 COT - HCPL - Medical Gas/Test Passed
06/23/2023 COT - HCBU - Building Final Passed
06/23/2023 COT - HCEL - Electrical Final Passed

Documents

File Name Document Type  
M23-5313 BUMCT MRI 3 MED GAS CERT_V1.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERTIFICATE-2023-06-29_V1-2023-07-07_V2.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERTIFICATE-2023-06-29_V1.PDF DOCUMENTS VIEW
BUMC MRI 3 RENOVATION - REVISED REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
20230131_BUMCT MRI CALCULATIONS_V1.PDF DOCUMENTS VIEW
CONS-20230131_BUMC-T_MRI-3_EQUIPMENT_REPLACEMENT-COMBINED_100%CDSET_SIGNED_V1.PDF DOCUMENTS VIEW