Permit: TC-COM-0125-00139
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
10096 E OLD VAIL RD
Address NEW:
10096 E OLD VAIL RD
Apply Date:
01/21/2025
Applicant:
John Mills
Description:
New Valvoline - minor auto service building
Permit Reviews
Permit Number - TC-COM-0125-00139
Permit Status: Inspections
Permit Description: New Valvoline - minor auto service building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/24/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/19/2025 | APPROVED |
| 05/19/2025 | RESTAMP - COMMERCIAL v.1 | 05/21/2025 | APPROVED |
| 03/18/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/15/2025 | REQUIRES RESUBMIT |
| 01/29/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/20/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0125-00139
Permit Status: Inspections
Permit Description: New Valvoline - minor auto service building
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 02/18/2025 | SPECIAL INSPECTION OF COLD-FORMED STEEL DECK IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OF CONCRETE CONSTRUCTION IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
| 02/18/2025 | SPECIAL INSPECTION OR STEEL CONSTRUCTION IS REQUIRED. |
| 02/19/2025 | PREFABRICATED WOOD TRUSSES- DESIGN PLANS MUST BE SUBMITTED AND APPROVED PRIOR TO FINAL INSPECTIONS. PLEASE SUBMIT TO STRUCTURAL ENGINEER FOR APPROVAL AND REVIEW STAMP PRIOR TO SUBMITTING TO THE CITY OF TUCSON |
| 04/14/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 05/05/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0125-00139
Permit Status: Inspections
Permit Description: New Valvoline - minor auto service building
| Date | Description | Comments |
|---|---|---|
| 01/29/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/06/2025 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 02/19/2025 | Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Pima County Industrial Wastewater Review Required - Kelsey.McMonagle@pima.gov or Adam.DeLaTorre@pima.gov for review and assessment of the proposed oil separator.. | |
| 01/29/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/06/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0125-00139
Permite Description: New Valvoline - minor auto service building
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2025 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 8-28-25: verified 1-1" Schedule 40 conduit with 1/0 copper attached to reinforcement. Okay to pour. |
| 09/16/2025 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | 9-16-25: canceled by contractor. |
| 08/28/2025 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | 8-28-25: reinforcement verified per plans-okay to pour pit walls . |
| 08/20/2025 | COT - LCPL - Sewer | N/A | Partial Pass | Partial pass. From sewer tie in up to building on test along with tracer wire and tape. Okay to backfill progress areas. Shading required. Pending tie into building. 8/20/2025 |
| 09/08/2025 | COT - LCBU - Preslab | N/A | Not Ready | 9-8-25: Arrived at location at approximately 1215 hours and spoke with a worker who indicated he had nothing for me to inspect today. Left site at 1225-reschedule when ready. |
| 12/02/2025 | COT - LCBU - Roof Nailing | N/A | Re-inspection required | 12-2-25: called point of contact at 1155 hours but received no answer. Arrived on site and waited over 12-2-25: electrical above ceiling approved. Okay to continue with TI.0 minutes for contractor. Left at 1216 hours-reschedule inspection. |
| 09/16/2025 | COT - LCME - Mechanical Intermediate | N/A | Canceled | 9-16-25: canceled by contractor. |
| BULD - Electrical Clearance | N/A | Requested | ||
| COT - LCPL - Plumbing Final | N/A | Requested |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0125-00139
Permit Description: New Valvoline - minor auto service building
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2025 | PDSD Building Division Pre-Construction Meeting | Passed | ||
| 08/14/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 10/03/2025 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 10/03/2025 | COT - LCPL - Rough Soil | Passed | ||
| 10/03/2025 | COT - LCPL - Yard Water Line | Passed | ||
| 10/03/2025 | COT - LCPL - Sewer | Passed | ||
| 10/29/2025 | COT - LCBU - Framing | Passed | Passed 10/29/25 ok to proceed |