Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Address:
192 S STONE AV
Apply Date:
01/09/2024
Applicant:
Cary Broschat
Description:
Install PV Solar parking canopies . 300.78 DC Kw / 232.00 AC Kw

Permit Reviews

Permit Number - TC-COM-0124-00048
Permit Status: Needs resubmittal
Permit Description: Install PV Solar parking canopies . 300.78 DC Kw / 232.00 AC Kw
Start Date Submittal Complete Date Status  
05/09/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/09/2024 REQUIRES RESUBMIT Review Details
01/09/2024 COMMERCIAL REVIEW - FULL v.1 01/10/2024 REQUIRES RESUBMIT Review Details
01/10/2024 COMMERCIAL REVIEW - FULL v.1 02/09/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0124-00048
Permit Status: Needs resubmittal
Permit Description: Install PV Solar parking canopies . 300.78 DC Kw / 232.00 AC Kw
Total Outstanding Activity Conditions - 5
Date Name
02/09/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
02/09/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
02/09/2024 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
02/09/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
02/09/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-0124-00048
Permit Status: Needs resubmittal
Permit Description: Install PV Solar parking canopies . 300.78 DC Kw / 232.00 AC Kw
Date Description Comments
02/09/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0124-00048
Permit Description: Install PV Solar parking canopies . 300.78 DC Kw / 232.00 AC Kw
Total Completed Inspections - 10
Date Description Inspector Results Comments
04/02/2024 COT - LCBU - Excavation/Rebar/Zoning Passed Footings for canopies A + B ok to pour.
04/11/2024 COT - CSOL - Electrical Underground Solar Project Passed
04/25/2024 COT - CSOL - Electrical Intermediate Solar Project Passed
04/30/2024 COT - CSOL - Grounding/Bonding Solar Project Passed Canopies 1 + 2
04/30/2024 COT - CSOL - Outdoor Lighting Solar Project Passed
05/09/2024 COT - CSOL - Electrical Final Solar Project Passed 5/9/24: Breaker at existing switchgear per plan ok to energize DGL.
05/10/2024 BULD - Electrical Clearance Passed Approved, DGC Clearance to TEP is required for the solar meter
05/10/2024 ENGR Engineering Final Passed
05/10/2024 COT - LCEL - Electrical Final Passed
05/10/2024 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-ST AUGUSTINE - PLANSET 2_V2.PDF DOCUMENTS VIEW
ST. AUGUSTINE - GEO REPORT 2_V2.PDF DOCUMENTS VIEW
ST. AUGUSTINE - STRUCTURAL CALCS 2_V2.PDF DOCUMENTS VIEW
ST. AUGUSTINE -SI INITIAL 2-2024-01-11_V2.PDF DOCUMENTS VIEW