Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0124-00001
Permit Details
Apply Date:
01/02/2024
Applicant:
Susan Carlson-Herdt
Description:
Install PV Solar Canopy 128.52 KW dc/ 100 KW ac (there will be a separate building permit application at this location. Both are included in TD-DEP-0923-00395)
Permit Reviews
Permit Number - TC-COM-0124-00001
Permit Status: Complete
Permit Description: Install PV Solar Canopy 128.52 KW dc/ 100 KW ac
(there will be a separate building permit application at this location. Both are included in TD-DEP-0923-00395)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/26/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/30/2024 | APPROVED |
05/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/13/2024 | APPROVED |
05/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/09/2024 | APPROVED |
01/30/2024 | RESTAMP - COMMERCIAL v.1 | 01/31/2024 | APPROVED |
01/02/2024 | COMMERCIAL REVIEW - FULL v.1 | 01/26/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0124-00001
Permit Status: Complete
Permit Description: Install PV Solar Canopy 128.52 KW dc/ 100 KW ac
(there will be a separate building permit application at this location. Both are included in TD-DEP-0923-00395)
Date | Description | Comments |
---|---|---|
01/26/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
01/26/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
01/26/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
01/26/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
01/26/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0124-00001
Permite Description: Install PV Solar Canopy 128.52 KW dc/ 100 KW ac
(there will be a separate building permit application at this location. Both are included in TD-DEP-0923-00395)
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/27/2024 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Partial Pass | Partial for the ufer ground at canopy A and column depth at canopy B , okay for concrete placement |
03/04/2024 | COT - CSOL - Electrical Underground Solar Project | N/A | Partial Pass | Partial pass for underground conduits from canopy A to B. Ok to backfill. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0124-00001
Permit Description: Install PV Solar Canopy 128.52 KW dc/ 100 KW ac
(there will be a separate building permit application at this location. Both are included in TD-DEP-0923-00395)
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/27/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Approved column foundations at canopy A and canopy B , okay for concrete placement | |
03/15/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved underground continued from the canopies to the equipment rack and SES location, okay to backfill all areas | |
04/24/2024 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
04/24/2024 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
05/01/2024 | ENGR Engineering Final | Passed | Completed as per plan | |
05/02/2024 | COT - CSOL - Electrical Final Solar Project | Passed | PV project complete. | |
05/02/2024 | COT - LCBU - Building Final | Passed | PV project complete. CLOSE PERMIT |
|
05/02/2024 | COT - LCEL - Electrical Final | Passed | ||
05/02/2024 | COT - CSOL - Electrical Progress Solar Project | Passed | ||
05/02/2024 | BULD - Electrical Clearance | Passed | 5/2/24 - Backfeed breaker installation complete. CLEAR DGC/DGL |