Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 02/29/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial for 1 underground electric riser at canopy A and 2 risers at canopy B, okay to backfill and for concrete placement for progress areas |
| 03/04/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial pass for underground conduits from canopy A to B. Ok to backfill. |
| 03/15/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Passed |
Approved underground continued from the canopies to the equipment rack and SES location, okay to backfill all areas |