Permit: TC-COM-0123-00534
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1620 W VALENCIA RD
Address NEW:
1620 W VALENCIA RD
Apply Date:
01/24/2023
Applicant:
Brandy Burke
Description:
Demo of an existing Taco Bell and Construction of a new Taco Bell.
Permit Reviews
Permit Number - TC-COM-0123-00534
Permit Status: Complete
Permit Description: Demo of an existing Taco Bell and Construction of a new Taco Bell.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/23/2023 | COMMERCIAL REVIEW - FULL v.3 | 06/08/2023 | REQUIRES RESUBMIT |
| 02/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/07/2023 | REQUIRES RESUBMIT |
| 12/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/21/2023 | APPROVED |
| 12/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/23/2023 | APPROVED |
| 04/20/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/18/2023 | REQUIRES RESUBMIT |
| 07/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/24/2023 | APPROVED |
| 12/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/15/2023 | APPROVED |
| 06/30/2023 | COMMERCIAL REVIEW - FULL v.4 | 07/13/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0123-00534
Permit Status: Complete
Permit Description: Demo of an existing Taco Bell and Construction of a new Taco Bell.
| Date | Description | Comments |
|---|---|---|
| 05/26/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 12/22/2023 | PASSED - Backflow Assembly Test Report | |
| 12/15/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/26/2023 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 12/15/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 05/26/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 05/26/2023 | Kitchen Hood Fire Suppression Designs must be submitted and approved prior to final. | |
| 12/15/2023 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 05/26/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 05/26/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 05/26/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00534
Permite Description: Demo of an existing Taco Bell and Construction of a new Taco Bell.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/02/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | Partial pass. Soffit at dining area and soda machine, west wall. Okay to proceed progress areas. 11/2/2023 |
| 11/15/2023 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 11/15/23: 1st smoke test on the grease duct passed. |
| 09/01/2023 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 9/1/23 Partial approval for you for connections under slab |
| 12/08/2023 | COT - HCPL - Backwater Valve | N/A | Not Applicable | |
| 09/15/2023 | COT - HCEL - Outdoor Lighting | N/A | Not Ready | wanted light pole bases. |
| COT - FCON - Hood System - Final | N/A | Not Ready | Called in wrong inspection. | |
| 12/22/2023 | COT - HCBU - Building Final | N/A | Partial Pass | okay for level 4 TCO |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00534
Permit Description: Demo of an existing Taco Bell and Construction of a new Taco Bell.
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/30/2023 | COT - HCBU - Preslab | Passed | 8/30/23: all passed ready to pour | |
| 09/06/2023 | COT - HCPL - Yard Water Line | Passed | 9/6/23: ok to backfill | |
| 09/06/2023 | COT - HCPL - Sewer | Passed | 9/6/23: connection from grease trap to sewer ok to backfill | |
| 09/12/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
| 09/15/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Light pole bases. | |
| 10/02/2023 | COT - HCBU - Roof Nailing | Passed | ||
| 10/02/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 10/13/2023 | COT - HCBU - Building Progress | Passed | Sheathing on pop outs. | |
| 10/20/2023 | COT - HCEL - Electrical Underground | Passed | 10/20/23: Electrical underground into directional sign on north east per plan, canopy, menu board, speaker all electrical underground per plan. | |
| 10/20/2023 | COT - HCPL - Rough Soil | Passed | 8/21/23 under slab complete to first clean out ok to backfill 8/28/23 rough soil for grease trap and site vent and waste lines, ok to cover 10/20/23: Electrical underground into directional sign on north east per plan, canopy, menu board, speaker all electrical underground per plan. |
|
| 10/31/2023 | COT - HCBU - Framing | Passed | ||
| 10/31/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
| 10/31/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 10/31/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
| 10/31/2023 | COT - HCME - Venting | Passed | ||
| 10/30/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 10/30/23: firewall at kitchen hood passed ok to proceed | |
| 11/02/2023 | COT - HCBU - Interior Shear Bracing | Passed | 11/2/2023. All drywall in place okay for tape and mud. | |
| 11/16/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 12/05/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 12/05/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 12/05/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 12/08/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
| 12/08/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
| 12/08/2023 | BULD - Electrical Clearance | Passed | 12/8/23: ECO TEP Clearance | |
| 12/08/2023 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 12/08/2023 | COT - BULD - SWG Clearance | Passed | 12/8/23: SWG CLEARANCE meter tag. | |
| TRSP - ROW - Final/Close-Out | Passed | |||
| 12/18/2023 | COT - HCPL - Plumbing Final | Passed | ||
| 12/18/2023 | COT - HCME - Mechanical Final | Passed | ||
| 12/18/2023 | COT - HCEL - Electrical Final | Passed | ||
| 12/18/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
| 12/18/2023 | COT - HCPL - Gas Final | Passed | ||
| 12/22/2023 | COT - FCON - Fire - Final | Passed | ||
| 12/19/2023 | COT - FCON - Hood System - Final | Passed | ||
| 01/17/2024 | ENGR Engineering Final | Passed | ||
| 01/17/2024 | COT - HCBU - CofO | Passed | ||
| 01/17/2024 | COT - HCBU - Building Final | Passed | ||
| 01/17/2024 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed |