Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
1150 N 7TH AV BLDG 1
Apply Date:
10/20/2022
Applicant:
Dennis Caldwell
Description:
Remodel existing bldg for multi-family use

Permit Reviews

Permit Number - T22CM08172
Permit Status: Complete
Permit Description: Remodel existing bldg for multi-family use
Start Date Submittal Complete Date Status  
10/20/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/20/2022 ACTIVE Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 12/12/2022 REQUIRES RESUBMIT Review Details
04/03/2023 RESTAMP - COMMERCIAL v.1 05/04/2023 APPROVED Review Details
01/06/2023 COMMERCIAL REVIEW - FULL v.2 02/03/2023 REQUIRES RESUBMIT Review Details
01/16/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/16/2025 APPROVED Review Details
04/16/2024 COMMERCIAL REVIEW - FULL v.2 05/16/2024 APPROVED Review Details
02/16/2023 COMMERCIAL REVIEW - FULL v.3 04/03/2023 APPROVED Review Details
03/11/2024 COMMERCIAL REVIEW - FULL v.1 03/11/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM08172
Permit Status: Complete
Permit Description: Remodel existing bldg for multi-family use
Date Description Comments
06/24/2024 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
06/24/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/16/2025 Post-Installed Anchor Inspection Report is required.
06/24/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM08172
Permite Description: Remodel existing bldg for multi-family use
Total Outstanding Inspections - 16
Last Inspection Date Description Inspector Results Comments
06/25/2024 FCON – Fire – Intermediate N/A Not Applicable
06/26/2024 COT - HCBU - Building Above Ceiling N/A Partial Pass Levels #2 and 3 West side of building.
06/26/2024 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Partial Pass Levels #2 and 3, room units and corridors of West side of building
06/26/2024 COT - HCBU - Framing N/A Partial Pass Levels #2 and 3, corridors and room units of West side of building.
06/26/2024 COT - HCBU - Interior Shear Bracing N/A Partial Pass Levels #2 and 3, corridors and room units in West side of building.
06/26/2024 COT - HCEL - Electrical Above Ceiling N/A Partial Pass Levels #2 and 3; corridors and room units in West side of building.
06/26/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass Levels #2 and 3, corridors and room units in West side of building.
06/26/2024 COT - LCME - Mechanical Above Ceiling N/A Partial Pass Levels #2 and 3, room units and corridors in West side of building.
06/26/2024 COT - LCME - Mechanical Intermediate N/A Partial Pass Levels #2 and 3, room units in West side of building.
06/26/2024 COT - LCPL - Plumbing Above Ceiling N/A Partial Pass Levels #2 and 3, corridors and room units in West side of building.
10/18/2024 COT - HCEL - Electrical Final N/A Partial Pass Request for electric clearance for meter sets (31) and power for building. Request forwarded to PDSD at 0915, 18 Oct 24.
10/30/2024 COT - LCPL - Plumbing Final N/A Not Ready
11/27/2024 BULD - Electrical Clearance N/A Not Ready Contractor cancelled…power to elevator is not ready.
COT - FCON - Alarm - Final N/A Not Ready
11/27/2024 COT - FCON - Sprinkler - Final N/A Re-inspection required Sprinkler heads in elevator hoistway shall be added, bell shall be added.
COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM08172
Permit Description: Remodel existing bldg for multi-family use
Total Completed Inspections - 20
Date Description Inspector Results Comments
07/10/2024 COT - LCPL - Plumbing Intermediate Passed
06/26/2024 COT - LCPL - Rough Soil Passed
08/06/2024 COT - HCBU - Building Above Ceiling Passed
08/06/2024 COT - HCBU - Firewall/Fire Barrier/Firestop Passed
08/06/2024 COT - HCBU - Framing Passed OK to insulate and cover walls.
08/06/2024 COT - HCBU - Interior Shear Bracing Passed Ok to insulate and cover walls.
08/06/2024 COT - HCEL - Electrical Above Ceiling Passed
08/06/2024 COT - HCEL - Electrical Intermediate Passed
08/06/2024 COT - LCME - Mechanical Above Ceiling Passed
08/06/2024 COT - LCME - Mechanical Intermediate Passed
08/06/2024 COT - LCPL - Plumbing Above Ceiling Passed
11/06/2024 COT - HCPL - Sewer Passed
11/21/2024 COT - HCEL - Electrical Final Passed
11/21/2024 COT - LCPL - Plumbing Final Passed
11/21/2024 COT - LCME - Mechanical Final Passed
12/11/2024 BULD - Electrical Clearance Passed No clearance required. Service is active.
12/23/2024 COT - HCBU - Building Final Passed
01/14/2025 COT - FCON - Alarm - Final Passed
01/14/2025 COT - FCON - Sprinkler - Final Passed
01/14/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
SPECIAL INSPECTION_FINAL-2025-01-15_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
20240305 - BUILDING 1 PLAN REVISION DESCRIPTION_V2.PDF DOCUMENTS VIEW
CONS-20240415 - BUILDING 1 CDS_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
3 OF 15 DP22-0290_V1.PDF DOCUMENTS VIEW
1_PROJECT MANUAL_V1.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
CONS-3_PLAN SET BLDG 1_V3.PDF DOCUMENTS VIEW
1_ SUPPLEMENTAL STRUCTURAL CALCULATION REV1_V1.PDF DOCUMENTS VIEW
3_NARRATIVE BLDG 1_V1.PDF DOCUMENTS VIEW
SIC FOR 8172 7TH AVE LOFTS-2023-01-03_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE_V1.PDF DOCUMENTS VIEW