Permit: T22CM08172

Parcel: 11508090A

Inspection Status: Not Ready

Inspection History: COT - HCEL - Electrical Final 

Date Description Inspector Results Comments
10/08/2024 COT - HCEL - Electrical Final  Not Ready
10/18/2024 COT - HCEL - Electrical Final  Partial Pass Request for electric clearance for meter sets (31) and power for building. Request forwarded to PDSD at 0915, 18 Oct 24.
10/22/2024 COT - HCEL - Electrical Final  Partial Pass Electric clearance for power/meter sets doe units #2100, 2200, 2300, 2400. Ok to set meters and energize service.
10/28/2024 COT - HCEL - Electrical Final  Partial Pass Inspection is for resubmittal of meter sets for both buildings. Resubmitted at 1430, 28 October 2024.
11/21/2024 COT - HCEL - Electrical Final  Passed