Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM08170
Permit Details
Apply Date:
10/20/2022
Applicant:
mariel grace
Description:
Ground-up car wash tunnel and associated facilities
Permit Reviews
Permit Number - T22CM08170
Permit Status: Needs resubmittal
Permit Description: Ground-up car wash tunnel and associated facilities
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/20/2022 | 3RD PARTY REVIEW - COMMERCIAL | 10/20/2022 | ACTIVE |
05/23/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/04/2024 | APPROVED |
02/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/28/2024 | REQUIRES RESUBMIT |
10/31/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/14/2023 | REQUIRES RESUBMIT |
09/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/13/2024 | REQUIRES RESUBMIT |
01/18/2024 | RESTAMP - COMMERCIAL v.1 | 01/25/2024 | APPROVED |
12/05/2023 | RESTAMP - COMMERCIAL v.1 | 12/05/2023 | APPROVED |
03/04/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/15/2024 | APPROVED |
04/08/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/16/2024 | REQUIRES RESUBMIT |
03/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/28/2024 | REQUIRES RESUBMIT |
11/30/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/05/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM08170
Permit Status: Needs resubmittal
Permit Description: Ground-up car wash tunnel and associated facilities
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/01/2023 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
Conditions
Permit Number - T22CM08170
Permit Status: Needs resubmittal
Permit Description: Ground-up car wash tunnel and associated facilities
Date | Description | Comments |
---|---|---|
12/01/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
12/01/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
07/28/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
12/01/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
12/01/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
12/01/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
12/01/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
12/01/2023 | Masonry Inspection Report submittal review is required. | |
03/20/2024 | Vacuume SystemDesigns must be submitted and approved prior to final. | |
12/01/2023 | Post-Installed Anchor Inspection Report is required. | |
07/28/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
12/01/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
06/04/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
12/01/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: T22CM08170
Permite Description: Ground-up car wash tunnel and associated facilities
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/03/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 4/3/24: Rebar for building stem walls is in place and properly tied. Okay to pour concrete. |
05/22/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 5/22/24: underground for two light poles on north side of property okay |
05/10/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 5/10/24: okay to backfill underground electrical for vacuum columns And vacuum inclosure |
06/11/2024 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 6/11/24: partial for interior framing waiting on RFI for 6x6 post substitute hood down. |
03/13/2024 | COT - HCPL - Sewer | N/A | Partial Pass | 3/13/24: okay to shade and backfill sewer |
02/21/2024 | COT - HCPL - Rough Soil | N/A | Partial Pass | 2/21/24: partial 30' Outside of building to the east water main riser |
04/03/2024 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | 4/3/24: Rebar for building stem walls is in place and properly tied. Okay to pour concrete. |
06/21/2024 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 6/21/24: hard duct at office area per plan ok to proceed with insulation. |
06/25/2024 | COT - HCPL - Plumbing Above Ceiling | N/A | Canceled | 6/25/24: canceled per contractor |
09/06/2024 | ENGR Engineering Final | N/A | Not Ready | This job has too much exterior work going on to even think about an engineering inspection yet. This site needs to be customer ready to consider a final inspection. |
09/05/2024 | COT - HCBU - Building Final | N/A | Not Ready | 9/4/24: not ready needed information |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: T22CM08170
Permit Description: Ground-up car wash tunnel and associated facilities
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/20/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
04/16/2024 | COT - LCPL - Yard Water Line | Passed | ||
05/06/2024 | COT - HCBU - Preslab | Passed | Trench drain forms are set with angle iron for grating properly secured to form. Rebar reinforcement is properly supported off of ground and wired together. Okay to pour concrete for slab. | |
05/29/2024 | COT - HCBU - Masonry Pregrout | Passed | 5/29/24: vacuum inclosure in northwest corner okay to grout and cap | |
06/18/2024 | COT - HCBU - Roof Nailing | Passed | ||
06/18/2024 | COT - HCBU - Framing | Passed | ||
06/21/2024 | COT - HCPL - Plumbing Roof Drains | Passed | 6/20/24: not ready supports not per plan, not under test. 6/21/24: passed |
|
07/19/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
07/19/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 7/19/24: okay to place concrete for two light posts south of building | |
07/19/2024 | COT - HCEL - Electrical Underground | Passed | 7/19/24: okay to back fill for two light post south of building. | |
08/05/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
08/05/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
08/05/2024 | COT - HCPL - Sewer | Passed | ||
08/05/2024 | COT - HCPL - Rough Soil | Passed | ||
08/05/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
08/05/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
08/05/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
08/05/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
08/19/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
08/26/2024 | COT - HCBU - Building Above Ceiling | Passed | 8/26/24: Grid ceiling framing is installed, electrical lights are installed and wired to the structure, mechanical ductwork and registers are installed. Okay to proceed with installation of ceiling tiles. | |
08/26/2024 | COT - HCME - Mechanical Above Ceiling | Passed | 8/26/24: Grid ceiling framing is installed, electrical lights are installed and wired to the structure, mechanical ductwork and registers are installed. Okay to proceed with installation of ceiling tiles. | |
08/26/2024 | COT - HCEL - Electrical Above Ceiling | Passed | 8/26/24: Grid ceiling framing is installed, electrical lights are installed and wired to the structure, mechanical ductwork and registers are installed. Okay to proceed with installation of ceiling tiles. | |
09/06/2024 | COT - HCME - Mechanical Final | Passed | ||
09/06/2024 | COT - FCON - Fire - Final | Passed | ||
09/06/2024 | COT - HCPL - Plumbing Final | Passed | ||
09/06/2024 | COT - HCEL - Electrical Final | Passed | ||
09/09/2024 | COT - HCEL - Outdoor Lighting | Passed | Outdoor lighting is properly installed and operational per plans and City regulations. | |
09/13/2024 | COT - HCBU - Building Final | Passed |