Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
5115 E VALENCIA RD
Apply Date:
10/15/2022
Applicant:
Chris Dornhecker
Description:
7,318 sq ft convenience store

Permit Reviews

Permit Number - T22CM07932
Permit Status: Complete
Permit Description: 7,318 sq ft convenience store
Start Date Submittal Complete Date Status  
10/15/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/15/2022 ACTIVE Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 12/12/2022 REQUIRES RESUBMIT Review Details
02/16/2023 COMMERCIAL REVIEW - FULL v.2 03/16/2023 REQUIRES RESUBMIT Review Details
06/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/21/2024 REQUIRES RESUBMIT Review Details
06/17/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/20/2024 REQUIRES RESUBMIT Review Details
10/23/2023 COMMERCIAL REVIEW - FULL v.3 10/23/2023 REQUIRES RESUBMIT Review Details
03/21/2023 COMMERCIAL REVIEW - FULL v.3 04/19/2023 REQUIRES RESUBMIT Review Details
06/24/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.4 06/25/2024 APPROVED Review Details
10/09/2023 COMMERCIAL REVIEW - FULL v.2 10/09/2023 REQUIRES RESUBMIT Review Details
05/31/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/10/2024 REQUIRES RESUBMIT Review Details
06/29/2023 COMMERCIAL REVIEW - FULL v.4 06/29/2023 REQUIRES RESUBMIT Review Details
07/05/2023 COMMERCIAL REVIEW - FULL v.5 07/14/2023 APPROVED Review Details
07/14/2023 RESTAMP - COMMERCIAL v.1 07/18/2023 APPROVED Review Details
11/14/2023 COMMERCIAL REVIEW - FULL v.4 11/22/2023 APPROVED Review Details
06/11/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/17/2024 APPROVED Review Details
06/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.3 06/24/2024 REQUIRES RESUBMIT Review Details
09/12/2023 COMMERCIAL REVIEW - FULL v.1 10/04/2023 REQUIRES RESUBMIT Review Details
06/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/26/2024 APPROVED Review Details
11/22/2023 RESTAMP - COMMERCIAL v.1 11/27/2023 APPROVED Review Details
12/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/11/2023 APPROVED Review Details
05/22/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/22/2024 APPROVED Review Details

Conditions

Permit Number - T22CM07932
Permit Status: Complete
Permit Description: 7,318 sq ft convenience store
Date Description Comments
07/18/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
06/26/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
06/24/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
05/20/2024 *Needs to pay Wastewater utility fee Invoice #P24WX01500 FOR QUIKTRIP prior to "Final" and prior to "Certificate of Occupancy" for City of Tucson Permit #T22CM07932* Project Description: QUIKTRIP - City of Tucson Permit #T22CM07932 -DP22-074 ISSUED WITH TYPE III CAPACITY APPROVAL #P22WC0213 DATED 6-6-22 CONNECTING TO EXISTING ON-SITE PRIVATE SEWER PER PDEQ DISCHARGE AUTHORIZATION #P22SD00098 DATED 12-15-23 CONNECTING TO NEW 1-1/2" WATER METER PER SITE UTILITY PLAN C150 PER DP22-074 AND PER COT UTILITY PLAN 1 PER #T22CM07932 For PCRWRD Wastewater Utility Fee approval for QuikTrip - City of Tucson Permit #T22CM07932 *Needs additionally PCRWRD Industrial Wastewater Control (IWC) review & approval of the grease interceptor Submit Site Plan and all plumbing drawings to: lucinda.hyatt@pima.gov - 520-724-6036 or kelsey.mcmonagle@pima.gov - 520-724-6073
06/07/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
04/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
06/07/2024 WATER STERILIZATION REPORT IS REQUIRED.
06/07/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM07932
Permite Description: 7,318 sq ft convenience store
Total Outstanding Inspections - 16
Last Inspection Date Description Inspector Results Comments
09/15/2023 COT - HCPL - Sewer N/A Partial Pass Manhole to interceptor.
10/12/2023 COT - HCBU - Masonry Pregrout N/A Partial Pass 1st lift.
10/13/2023 COT - HCEL - Grounding/Bonding N/A Partial Pass 5 Light pole bases on West side.
10/13/2023 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 5 Light pole bases on West side.
11/01/2023 COT - HCEL - Electrical Underground N/A Partial Pass
11/21/2023 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 11/21/23: men's & women's restrooms.
11/30/2023 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 11/21/23: men's & women's restrooms.
11/30/23: kitchen & prep area.
11/30/2023 COT - HCEL - Electrical Intermediate N/A Partial Pass 11/30/23: kitchen & prep area.
01/10/2024 COT - HCME - Kitchen Hood N/A Partial Pass 1/10/24: Kitchen hood smoke test passed, 1st layer of wrap passed, 2nd layer passed. pending final
11/30/2023 COT - HCBU - Building Progress N/A Partial Pass
11/21/2023 COT - HCBU - Framing N/A Partial Pass 11/21/23: men's & women's restrooms.
10/11/2023 COT - HCEL - Outdoor Lighting N/A Partial Pass Total of 8 light pole basis for sight lighting, rebar per plan per detail A13 (S530) Grounding detail A8(E007). Okay for concrete placement. 10/11/2023
11/14/2023 COT - HCME - Mechanical Progress N/A Partial Pass 11/14/23: main supply and return to 4 units hard duct complete and per plan, ok to proceed with runoff's.
11/30/2023 COT - HCPL - Plumbing Intermediate N/A Partial Pass 11/30/23: kitchen & prep area.
09/29/2023 COT - HCPL - Plumbing Roof Drains N/A Not Ready 9/29/23: not ready
09/29/2023 COT - HCPL - Rough Soil N/A Partial Pass 9/29/23: plumbing waste and vent in building all per plan and under test.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM07932
Permit Description: 7,318 sq ft convenience store
Total Completed Inspections - 28
Date Description Inspector Results Comments
10/04/2023 COT - HCBU - Preslab Passed
10/20/2023 COT - HCBU - Masonry Pregrout Passed Screen walls and 5 columns on North side of Fuel Canopy.

10/10/23 Ok to continue

1st lift.

3rd lift. At main building all around. Rebar per plan. Okay to grout. 10/17/2023

10/20/23: final lift at main building rebar per plan ok to grout.
11/01/2023 COT - HCEL - Grounding/Bonding Passed
11/01/2023 COT - HCBU - Excavation/Rebar/Zoning Passed
11/14/2023 COT - HCBU - Roof Nailing Passed
11/21/2023 COT - HCEL - Electrical Progress Passed
11/21/2023 COT - HCPL - Plumbing Progress Passed
03/20/2024 COT - HCBU - Building Above Ceiling Passed
03/20/2024 COT - HCME - Mechanical Above Ceiling Passed
04/22/2024 BULD - Electrical Clearance Passed 4/22/24: ECO TEP CLEARANCE
06/24/2024 COT - BULD - SWG Clearance Passed
06/24/2024 COT - HCBU - Building Progress Passed
06/24/2024 COT - HCBU - Exterior Clips/Sheathing Passed
06/24/2024 COT - HCBU - Framing Passed
06/24/2024 COT - HCBU - Interior Shear Bracing Passed
06/24/2024 COT - HCEL - Electrical Final Passed
06/24/2024 COT - HCEL - Outdoor Lighting Passed
06/24/2024 COT - HCME - Mechanical Final Passed T&B report uploaded and in review. 6/24/2024
06/24/2024 COT - HCME - Mechanical Intermediate Passed
06/24/2024 COT - HCME - Mechanical Progress Passed
06/24/2024 COT - HCPL - Backwater Valve Passed
06/24/2024 COT - HCPL - Plumbing Final Passed Chlorination report uploaded and in review. 6/24/2024
06/24/2024 COT - HCPL - Plumbing Intermediate Passed
06/24/2024 COT - HCPL - Plumbing Roof Drains Passed
06/24/2024 COT - HCPL - Rough Soil Passed
06/25/2024 COT - FCON - Fire - Final Passed
06/27/2024 COT - HCBU - Building Final Passed
06/28/2024 SITE - Zoning Final Passed