Permit: T22CM07932
Permit Details
Apply Date:
10/15/2022
Applicant:
Jonathan Naut
Description:
7,318 sq ft convenience store
Permit Reviews
Permit Number - T22CM07932
Permit Status: Complete
Permit Description: 7,318 sq ft convenience store
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/15/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/15/2022 | ACTIVE |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/12/2022 | REQUIRES RESUBMIT |
02/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/16/2023 | REQUIRES RESUBMIT |
06/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/21/2024 | REQUIRES RESUBMIT |
06/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/20/2024 | REQUIRES RESUBMIT |
10/23/2023 | COMMERCIAL REVIEW - FULL v.3 | 10/23/2023 | REQUIRES RESUBMIT |
03/21/2023 | COMMERCIAL REVIEW - FULL v.3 | 04/19/2023 | REQUIRES RESUBMIT |
06/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 06/25/2024 | APPROVED |
10/09/2023 | COMMERCIAL REVIEW - FULL v.2 | 10/09/2023 | REQUIRES RESUBMIT |
05/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/10/2024 | REQUIRES RESUBMIT |
06/29/2023 | COMMERCIAL REVIEW - FULL v.4 | 06/29/2023 | REQUIRES RESUBMIT |
07/05/2023 | COMMERCIAL REVIEW - FULL v.5 | 07/14/2023 | APPROVED |
07/14/2023 | RESTAMP - COMMERCIAL v.1 | 07/18/2023 | APPROVED |
11/14/2023 | COMMERCIAL REVIEW - FULL v.4 | 11/22/2023 | APPROVED |
06/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/17/2024 | APPROVED |
06/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 06/24/2024 | REQUIRES RESUBMIT |
09/12/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/04/2023 | REQUIRES RESUBMIT |
06/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/26/2024 | APPROVED |
11/22/2023 | RESTAMP - COMMERCIAL v.1 | 11/27/2023 | APPROVED |
12/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/11/2023 | APPROVED |
05/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/22/2024 | APPROVED |
Conditions
Permit Number - T22CM07932
Permit Status: Complete
Permit Description: 7,318 sq ft convenience store
Date | Description | Comments |
---|---|---|
07/18/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
06/26/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
06/24/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
05/20/2024 | *Needs to pay Wastewater utility fee Invoice #P24WX01500 FOR QUIKTRIP prior to "Final" and prior to "Certificate of Occupancy" for City of Tucson Permit #T22CM07932* Project Description: QUIKTRIP - City of Tucson Permit #T22CM07932 -DP22-074 ISSUED WITH TYPE III CAPACITY APPROVAL #P22WC0213 DATED 6-6-22 CONNECTING TO EXISTING ON-SITE PRIVATE SEWER PER PDEQ DISCHARGE AUTHORIZATION #P22SD00098 DATED 12-15-23 CONNECTING TO NEW 1-1/2" WATER METER PER SITE UTILITY PLAN C150 PER DP22-074 AND PER COT UTILITY PLAN 1 PER #T22CM07932 For PCRWRD Wastewater Utility Fee approval for QuikTrip - City of Tucson Permit #T22CM07932 *Needs additionally PCRWRD Industrial Wastewater Control (IWC) review & approval of the grease interceptor Submit Site Plan and all plumbing drawings to: lucinda.hyatt@pima.gov - 520-724-6036 or kelsey.mcmonagle@pima.gov - 520-724-6073 | |
06/07/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
04/03/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
06/07/2024 | WATER STERILIZATION REPORT IS REQUIRED. | |
06/07/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07932
Permite Description: 7,318 sq ft convenience store
Total Outstanding Inspections - 16
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/15/2023 | COT - HCPL - Sewer | N/A | Partial Pass | Manhole to interceptor. |
10/12/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 1st lift. |
10/13/2023 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 5 Light pole bases on West side. |
10/13/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 5 Light pole bases on West side. |
11/01/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
11/21/2023 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 11/21/23: men's & women's restrooms. |
11/30/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 11/21/23: men's & women's restrooms. 11/30/23: kitchen & prep area. |
11/30/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 11/30/23: kitchen & prep area. |
01/10/2024 | COT - HCME - Kitchen Hood | N/A | Partial Pass | 1/10/24: Kitchen hood smoke test passed, 1st layer of wrap passed, 2nd layer passed. pending final |
11/30/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | |
11/21/2023 | COT - HCBU - Framing | N/A | Partial Pass | 11/21/23: men's & women's restrooms. |
10/11/2023 | COT - HCEL - Outdoor Lighting | N/A | Partial Pass | Total of 8 light pole basis for sight lighting, rebar per plan per detail A13 (S530) Grounding detail A8(E007). Okay for concrete placement. 10/11/2023 |
11/14/2023 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 11/14/23: main supply and return to 4 units hard duct complete and per plan, ok to proceed with runoff's. |
11/30/2023 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 11/30/23: kitchen & prep area. |
09/29/2023 | COT - HCPL - Plumbing Roof Drains | N/A | Not Ready | 9/29/23: not ready |
09/29/2023 | COT - HCPL - Rough Soil | N/A | Partial Pass | 9/29/23: plumbing waste and vent in building all per plan and under test. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07932
Permit Description: 7,318 sq ft convenience store
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/04/2023 | COT - HCBU - Preslab | Passed | ||
10/20/2023 | COT - HCBU - Masonry Pregrout | Passed | Screen walls and 5 columns on North side of Fuel Canopy. 10/10/23 Ok to continue 1st lift. 3rd lift. At main building all around. Rebar per plan. Okay to grout. 10/17/2023 10/20/23: final lift at main building rebar per plan ok to grout. |
|
11/01/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
11/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
11/14/2023 | COT - HCBU - Roof Nailing | Passed | ||
11/21/2023 | COT - HCEL - Electrical Progress | Passed | ||
11/21/2023 | COT - HCPL - Plumbing Progress | Passed | ||
03/20/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
03/20/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/22/2024 | BULD - Electrical Clearance | Passed | 4/22/24: ECO TEP CLEARANCE | |
06/24/2024 | COT - BULD - SWG Clearance | Passed | ||
06/24/2024 | COT - HCBU - Building Progress | Passed | ||
06/24/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
06/24/2024 | COT - HCBU - Framing | Passed | ||
06/24/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
06/24/2024 | COT - HCEL - Electrical Final | Passed | ||
06/24/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
06/24/2024 | COT - HCME - Mechanical Final | Passed | T&B report uploaded and in review. 6/24/2024 | |
06/24/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
06/24/2024 | COT - HCME - Mechanical Progress | Passed | ||
06/24/2024 | COT - HCPL - Backwater Valve | Passed | ||
06/24/2024 | COT - HCPL - Plumbing Final | Passed | Chlorination report uploaded and in review. 6/24/2024 | |
06/24/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
06/24/2024 | COT - HCPL - Plumbing Roof Drains | Passed | ||
06/24/2024 | COT - HCPL - Rough Soil | Passed | ||
06/25/2024 | COT - FCON - Fire - Final | Passed | ||
06/27/2024 | COT - HCBU - Building Final | Passed | ||
06/28/2024 | SITE - Zoning Final | Passed |