Permit: T22CM07730
Permit Details
Apply Date:
10/07/2022
Applicant:
Description:
SFR MERI213021 T21-M0065
Outstanding Activity Conditions
Permit Number - T22CM07730
Permit Status: Issued
Permit Description: SFR MERI213021 T21-M0065
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
10/07/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
10/07/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
10/07/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
10/07/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2021-022/P21WP00211 IS ACCEPTED AND RELEASED BY PCRWRD |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07730
Permite Description: SFR MERI213021 T21-M0065
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
01/23/2023 | COT - RSPL - Yard Water Line | N/A | Partial Pass | lines need to be under pressure. |
01/23/2023 | COT - RSPL - Sewer | N/A | Partial Pass | partial connection to hub set. okay to backfill. shading required |
04/14/2023 | RSBU - Building Final | N/A | Partial Pass | 4-14-23: A/C Unit is connected and energized for office area. Yard water line is connected and under pressure. Chad Ritter has it turned off at meter to prevent people from using the facilities inside until 4-24-23 when they should have permission to use sewer. Okay to issue a temporary Level 2 Certificate of Occupancy. |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07730
Permit Description: SFR MERI213021 T21-M0065
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/23/2023 | COT - RSPL - Rough Soil | Passed | okay to backfill. shading required | |
01/26/2023 | COT - RSEL - Electrical Underground | Passed | ||
01/26/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
01/26/2023 | COT - RSBU - Preslab | Passed | ||
01/27/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
02/02/2023 | COT - RSBU - Roof Nailing | Passed | ||
02/06/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/13/2023 | COT - LCBU - Framing | Passed | ||
02/13/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
02/13/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
02/13/2023 | RSME - Mechanical Progress | Passed | ||
02/13/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
02/13/2023 | COT - RSEL - Construction Power | Passed | clearance for TEP ECO. | |
02/27/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
04/03/2023 | COT - BULD - SWG Clearance | Passed | Gas appliances are installed, shut off valves are in place. Okay to install meter. | |
04/13/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
04/14/2023 | COT - RSEL - Electrical Final | Passed | 4-14-23: A/C Unit is connected and energized for office area. Yard water line is connected and under pressure. Chad Ritter has it turned off at meter to prevent people from using the facilities inside until 4-24-23 when they should have permission to use sewer. Okay to issue a temporary Level 2 Certificate of Occupancy. | |
04/14/2023 | COT - RSME - Mechanical Final | Passed | 4-14-23: A/C Unit is connected and energized for office area. Yard water line is connected and under pressure. Chad Ritter has it turned off at meter to prevent people from using the facilities inside until 4-24-23 when they should have permission to use sewer. Okay to issue a temporary Level 2 Certificate of Occupancy. |