Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM07688
Permit Details
Apply Date:
10/06/2022
Applicant:
Jorge Teran
Description:
SFR DRHOH30M21 T21-M0041
Permit Reviews
Permit Number - T22CM07688
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/22/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM07688
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
10/06/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
10/06/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2018-112(P21WP00113) IS ACCEPTED ANDRELEASED BY PCRWRD |
Conditions
Permit Number - T22CM07688
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Date | Description | Comments |
---|---|---|
10/06/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
06/21/2023 | Post-Tension Inspection Report is required. | |
06/21/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07688
Permite Description: SFR DRHOH30M21 T21-M0041
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/28/2023 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
04/20/2023 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | Not ready provide DWV test throughout second floor. Smoke detectors need to be 3’ away from bathroom doors. Space pex lines 12” minimum from any can lights. |
03/30/2023 | COT - LCBU - Framing | N/A | Partial Pass | partial per intermediates. 3/30/2023 |
04/20/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | Not ready provide DWV test throughout second floor. Smoke detectors need to be 3’ away from bathroom doors. Space pex lines 12” minimum from any can lights. |
03/28/2023 | COT - RSEL - Construction Power | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07688
Permit Description: SFR DRHOH30M21 T21-M0041
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/15/2023 | COT - RSBU - Preslab | Passed | ||
03/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
03/15/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
03/15/2023 | COT - RSEL - Electrical Underground | Passed | ||
03/30/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | Corrections were made. 3/30/2023 | |
04/20/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
04/21/2023 | COT - LCPL - Plumbing Intermediate | Passed | Approved. Corrections were made. 4/21/2023 | |
04/21/2023 | COT - LCBU - Framing | Passed | Approved. Corrections were made. 4/21/2023 | |
04/21/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Approved. Corrections were made. 4/21/2023 | |
04/21/2023 | COT - RSEL - Construction Power | Passed | Approved. Clearance for TEP ECO. 4/21/2023 | |
05/09/2023 | COT - HCBU - Interior Shear Bracing | Passed | Duplicate inspection. 5/9/2023 | |
05/09/2023 | COT - RSBU - Interior Shear Bracing | Passed | Approved 5/9/2023 | |
05/30/2023 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 5/30/202 | |
07/20/2023 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 7/20/2023 | |
07/28/2023 | COT - RSPL - Plumbing Final | Passed | ||
07/28/2023 | ENGR Engineering Final | Passed | ||
07/28/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
07/28/2023 | COT - RSEL - Electrical Final | Passed | ||
07/28/2023 | COT - RSME - Mechanical Final | Passed | ||
07/28/2023 | RSME - Mechanical Progress | Passed | ||
01/11/2024 | RSBU - Building Final | Passed | Duplicate inspection. 1/11/2024 | |
06/25/2024 | COT - RSPL - Yard Water Line | Passed | ||
06/25/2024 | COT - RSPL - Sewer | Passed | ||
06/25/2024 | COT - RSPL - Rough Soil | Passed |