Permit: T22CM07378
Permit Details
Apply Date:
09/26/2022
Applicant:
Michelle McConnell
Description:
New parking lot for future Reid Park Zoo
Permit Reviews
Permit Number - T22CM07378
Permit Status: Complete
Permit Description: New parking lot for future Reid Park Zoo
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/26/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/20/2022 | COMPLETED |
04/05/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/08/2023 | APPROVED |
05/03/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/03/2023 | REQUIRES RESUBMIT |
05/08/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/19/2023 | APPROVED |
04/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/13/2023 | APPROVED |
03/02/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/06/2023 | APPROVED |
04/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/19/2024 | APPROVED |
01/05/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/30/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM07378
Permit Status: Complete
Permit Description: New parking lot for future Reid Park Zoo
Date | Description | Comments |
---|---|---|
03/28/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
03/06/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
03/28/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
03/28/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
03/28/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07378
Permite Description: New parking lot for future Reid Park Zoo
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/11/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 6/15/23: reinforcing and grounding in 7 light pole bases are approved as noted on page CA1.1P . 7/10/23: reinforcing and grounding in 7 light pole bases are approved as noted on page CA1.1P8 8/16/23 material bins inspections via 3rd party 9/11/23: reinforcing and grounding in light pole bases 1-8 area 2 approved per detail |
10/30/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 10/30/23 reinforcing and grounding in 7 light pole bases are approved #17 as noted on CA1.1P. 19 was not inspected but there was concrete in the hole, please correct and call for inspection |
12/18/2023 | COT - HCEL - Outdoor Lighting | N/A | Not Ready | |
10/30/2023 | BULD - Electrical Clearance | N/A | Not Ready | |
05/31/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07378
Permit Description: New parking lot for future Reid Park Zoo
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
09/25/2023 | COT - HCEL - Electrical Progress | Passed | ||
12/18/2023 | COT - FCON - Fire - Final | Passed | ||
03/12/2024 | COT - HCEL - Electrical Underground | Passed | ||
04/01/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
03/20/2024 | COT - HCEL - Electrical Final | Passed | ||
04/04/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
04/03/2024 | ENGR Engineering Final | Passed | This permit is ready for a TCO4 on the parking lot and driveline. Contractor will fence off the fire line curb down to the back side of the ZOO sign and across to the grass area to close off the next phase of construction, (the old parking lot). This will also allow for pedestrian access and vehicles to enter the new parking lot and have access to both buildings. Van accessible spaces to the right side of cross hatch areas are not right for van accessible access without forcing an accessible van to back into a space. The van accessible space on the south side of the pool bld. at the entrance is also forcing someone to back into the space. |
|
04/24/2024 | COT - HCBU - Building Final | Passed |