Permit: T22CM06960
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6818 S COUNTRY CLUB RD UNIT 170
Address NEW:
6818 S COUNTRY CLUB RD UNIT 170
Apply Date:
09/12/2022
Applicant:
Description:
TI: TUCSON AIRPORT CENTER
Permit Reviews
Permit Number - T22CM06960
Permit Status: Complete
Permit Description: TI: TUCSON AIRPORT CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/12/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/11/2022 | ACTIVE |
| 11/22/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/10/2023 | REQUIRES RESUBMIT |
| 06/29/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/30/2023 | APPROVED |
| 01/30/2023 | COMMERCIAL REVIEW - FULL v.2 | 02/16/2023 | APPROVED |
Conditions
Permit Number - T22CM06960
Permit Status: Complete
Permit Description: TI: TUCSON AIRPORT CENTER
| Date | Description | Comments |
|---|---|---|
| 12/23/2022 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 09/12/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE | |
| 12/23/2022 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06960
Permite Description: TI: TUCSON AIRPORT CENTER
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/07/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 06/07/2023 | COT - HCPL - Gas Final | N/A | Not Applicable | |
| 06/07/2023 | COT - HCPL - Gas Pressure Test | N/A | Not Applicable | |
| 06/07/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Exit sign not illuminated. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06960
Permit Description: TI: TUCSON AIRPORT CENTER
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2023 | COT - HCPL - Plumbing Intermediate | Passed | Plumbing rough in is complete, waste and vent pipes are under water test. | |
| 04/04/2023 | COT - HCBU - Interior Shear Bracing | Passed | interior walls ok to tape | |
| 04/04/2023 | COT - HCBU - Framing | Passed | ||
| 04/05/2023 | COT - HCPL - Plumbing Progress | Passed | Rough in is complete. | |
| 04/14/2023 | COT - HCEL - Electrical Intermediate | Passed | Electrical rough in above ceiling is complete. Okay to install ceiling grid and tile. | |
| 04/14/2023 | COT - HCME - Mechanical Intermediate | Passed | HVAC rough-in is complete above ceiling. Okay to install ceiling grid and tile. | |
| 04/14/2023 | COT - HCEL - Electrical Above Ceiling | Passed | Electrical rough in above ceiling is complete. Okay to install ceiling grid and tile. | |
| 06/07/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 06/07/2023 | SITE - Zoning Final | Passed | ||
| 06/07/2023 | COT - HCEL - Electrical Progress | Passed | ||
| 06/23/2023 | COT - HCBU - Building Final | Passed | ||
| 06/23/2023 | COT - FCON - Fire - Final | Passed | ||
| 06/23/2023 | COT - HCEL - Electrical Final | Passed | ||
| 06/23/2023 | COT - HCME - Mechanical Final | Passed | ||
| 06/23/2023 | COT - HCPL - Plumbing Final | Passed | ||
| 06/23/2023 | COT - HCBU - Building Progress | Passed | ||
| 06/23/2023 | COT - HCME - Mechanical Progress | Passed | ||
| 06/23/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 06/23/2023 | COT - HCPL - Rough Soil | Passed |