Permit: T22CM06586
Permit Details
Apply Date:
08/25/2022
Applicant:
Description:
NEW TENANT IMPROVEMENT OFFICE INSIDE EXISTING STORAGE BUILDING.
Permit Reviews
Permit Number - T22CM06586
Permit Status: Complete
Permit Description: NEW TENANT IMPROVEMENT OFFICE INSIDE EXISTING STORAGE BUILDING.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/25/2022 | COMMERCIAL - TI | 09/21/2022 | COMPLETED |
| 09/30/2022 | RESUBMITTAL | 10/06/2022 | COMPLETED |
| 12/09/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/09/2022 | REQUIRES RESUBMIT |
| 05/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/08/2023 | APPROVED |
| 03/28/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/07/2023 | APPROVED |
Conditions
Permit Number - T22CM06586
Permit Status: Complete
Permit Description: NEW TENANT IMPROVEMENT OFFICE INSIDE EXISTING STORAGE BUILDING.
| Date | Description | Comments |
|---|---|---|
| 08/25/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE | |
| 10/04/2022 | WATER DISINFECTION REPORT REQUIRED | |
| 10/04/2022 | AIR BALANCE REPORT REQUIRED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06586
Permite Description: NEW TENANT IMPROVEMENT OFFICE INSIDE EXISTING STORAGE BUILDING.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06586
Permit Description: NEW TENANT IMPROVEMENT OFFICE INSIDE EXISTING STORAGE BUILDING.
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/30/2022 | COT - LCPL - Rough Soil | Passed | okay to backfill. shading required. | |
| 11/30/2022 | COT - LCEL - Electrical Underground | Passed | not applicable | |
| 11/30/2022 | COT - LCEL - Grounding/Bonding | Passed | not applicable | |
| 12/01/2022 | COT - LCBU - Preslab | Passed | okay to pour concrete | |
| 01/04/2023 | COT - LCBU - Framing | Passed | ||
| 01/23/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 01/23/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/23/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/30/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 04/14/2023 | COT - LCBU - Building Above Ceiling | Passed | Electrical, plumbing, and mechanical above ceiling is complete. Okay to install ceiling tiles. | |
| 04/14/2023 | COT - LCEL - Electrical Above Ceiling | Passed | Electrical above ceiling is complete, all j-boxes are properly marked. Okay to install ceiling tiles. | |
| 04/14/2023 | COT - LCBU - Building Progress | Passed | All work is in punch list status. | |
| 04/14/2023 | COT - LCME - Mechanical Final | Passed | Mechanical equipment is installed and has been tested. | |
| 04/24/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 04/24/2023 | COT - LCEL - Electrical Final | Passed | ||
| 04/24/2023 | COT - LCBU - Building Final | Passed | ||
| 04/24/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 04/24/2023 | COT - FCON - Fire - Final | Passed |