Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM06474
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6420 E 22ND ST BLDG 1
Address NEW:
6420 E 22ND ST BLDG 1
Apply Date:
08/22/2022
Applicant:
Description:
TI: Existing Auto Dealership - Building 1
Permit Reviews
Permit Number - T22CM06474
Permit Status: Complete
Permit Description: TI: Existing Auto Dealership - Building 1
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/22/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/21/2022 | COMPLETED |
| 06/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/27/2023 | APPROVED |
| 11/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/14/2023 | REQUIRES RESUBMIT |
| 11/05/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/20/2023 | APPROVED |
| 03/13/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/16/2024 | APPROVED |
| 02/14/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/06/2024 | APPROVED |
| 07/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/30/2024 | APPROVED |
| 01/16/2024 | RESTAMP - COMMERCIAL v.1 | 01/16/2024 | APPROVED |
| 04/18/2024 | COMMERCIAL REVIEW - FULL v.1 | 05/16/2024 | APPROVED |
| 01/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/16/2024 | APPROVED |
| 02/26/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/27/2025 | APPROVED |
Conditions
Permit Number - T22CM06474
Permit Status: Complete
Permit Description: TI: Existing Auto Dealership - Building 1
| Date | Description | Comments |
|---|---|---|
| 04/17/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 04/17/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 07/30/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 04/17/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/17/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 04/17/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 09/17/2024 | Provide verification of Pima County sewer connection review, IWC approval and payment of associated fees. Please contact Pima County DSD-Building Codes/Wastewater (520)-724-6503 | |
| 04/17/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 04/17/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 04/17/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 04/17/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06474
Permite Description: TI: Existing Auto Dealership - Building 1
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2023 | COT - HCBU - Roof Nailing | N/A | Not Applicable | |
| 09/29/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Canceled | 6/21/23: footings for new car delivery canopy approved to pour. Footings for north side mats at entrance approved to pour. 8/17/23: footing for entrance ramp on north side of building. Pour-back over electric conduit on showroom floor. 9/18/23: 4 reinforced pads and footing reinforcing at Service Drive approved. 9/29/23: inspection cancelled per A.J. |
| 09/07/2023 | COT - HCBU - Building Progress | N/A | Canceled | |
| 12/26/2023 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 12/26/23 customer work service, advisors, service, advisors, managers, office, parts, and cashier area |
| 10/06/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 9/26/23: stem reinforcing for new CMU walls at the New Service Drive Extension. 9/28/23: 1st lift at New Service Drive extension 9/29/23: 2nd lift at New Service Drive extension. 10/2/23: 3rd lift at New Service Drive extension. 10/6/23: top-out lift at New Service extension. |
| 10/24/2024 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | N/A | Partial Pass | 8" air gap in meeting room. |
| 12/13/2023 | COT - HCBU - Framing | N/A | Partial Pass | 12/13/23: partial for cashier parts display and advisors area framing okay to cover |
| 06/28/2024 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Sprinklers in north building east of car wash approved. |
| 07/23/2024 | ENGR Engineering Final | N/A | Not Ready | This will be recalled for next week as a TCO4 release for the left side of the service garage, parking on the east side of same to include the ADA parking and accessible lane into and around to the front of the building. Behind the garage they will fence off the exit from the garage to the actual service area. New ADA non accessible sign and yellow warning stripe will be painted prior to inspection and all construction materials will be removed. |
| 07/31/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Showroom and advisor area approved for level 4 TCO. South buildings need to be approved still. South riser needs to be tied into FA. |
| 10/11/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | Existing SES partial for lines to Panels S-M, primaries for new SES panel from panel to fire line valve. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06474
Permit Description: TI: Existing Auto Dealership - Building 1
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2023 | COT - HCEL - Electrical Progress | Passed | ||
| 02/13/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 05/10/2024 | BULD - Electrical Clearance | Passed | Approved 1200A SES cabinet "H" connected to transformer, ECO Clearance to TEP is required | |
| 07/22/2024 | COT - HCME - Mechanical Final | Passed | ||
| 07/22/2024 | COT - HCBU - Building Final | Passed | ||
| 07/22/2024 | COT - HCBU - TCO | Passed | Level Three for Showroom and Service Writer. | |
| 07/22/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 08/30/2024 | COT - HCBU - Building Progress | Passed | ||
| 10/16/2024 | COT - HCEL - Outdoor Lighting | Passed | 10/16/24: parking lot lights north side of building complete. | |
| 11/04/2024 | COT - HCBU - Interior Shear Bracing | Passed | Finals for service tech bathrooms. | |
| 11/20/2024 | COT - HCBU - Masonry Pregrout | Passed | 11/20/24: okay to grout 2nd lift of wall between office area and service bay on south side. | |
| 12/03/2024 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | Passed | Southwest service bays. East and west end connecting to existing footers approved. Okay for concrete placement. 12/3/2024 | |
| 12/09/2024 | COT - HCBU - Framing | Passed | ||
| 12/12/2024 | COT - HCPL - Rough Soil | Passed | ||
| 12/31/2024 | COT - HCBU - Preslab | Passed | 12-31-24, rebar verified at 18 o.c.. Okay to pour remainder of concrete at south service bay. | |
| 02/13/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 03/04/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 03/04/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
| 03/04/2025 | COT - HCPL - Plumbing Progress | Passed | ||
| 03/04/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 02/27/2025 | ENGR Engineering Final | Passed | ||
| 03/04/2025 | COT - HCME - Mechanical Intermediate | Passed | ||
| 02/27/2025 | COT - FCON - Fire - Final | Passed | ||
| 03/04/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 03/04/2025 | COT - HCEL - Electrical Underground | Passed | ||
| 03/04/2025 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 03/04/2025 | COT - HCEL - Electrical Final | Passed | ||
| 03/04/2025 | COT - LCBU - Masonry Pregrout | Passed | ||
| 03/04/2025 | COT - HCME - Mechanical Progress | Passed | ||
| 03/04/2025 | COT - HCPL - Plumbing Above Ceiling | Passed |