Permit Number - T22CM06474
Permit Status: Fees paid
Permit Description: TI: Existing Auto Dealership - Building 1
Start Date Submittal Complete Date Status  
08/22/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 09/21/2022 COMPLETED Review Details
06/22/2023 COMMERCIAL REVIEW - FULL v.1 06/27/2023 APPROVED Review Details
11/08/2023 COMMERCIAL REVIEW - FULL v.1 12/14/2023 REQUIRES RESUBMIT Review Details
11/05/2022 COMMERCIAL REVIEW - FULL v.1 01/20/2023 APPROVED Review Details
03/13/2024 COMMERCIAL REVIEW - FULL v.1 04/16/2024 APPROVED Review Details
02/14/2024 COMMERCIAL REVIEW - FULL v.1 03/06/2024 APPROVED Review Details
07/29/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/30/2024 APPROVED Review Details
01/16/2024 RESTAMP - COMMERCIAL v.1 01/16/2024 APPROVED Review Details
04/18/2024 COMMERCIAL REVIEW - FULL v.1 05/16/2024 APPROVED Review Details
01/04/2024 COMMERCIAL REVIEW - FULL v.2 01/16/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM06474
Permit Status: Fees paid
Permit Description: TI: Existing Auto Dealership - Building 1
Total Outstanding Activity Conditions - 8
Date Name
04/17/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/17/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
07/30/2024 Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.

Conditions

Permit Number - T22CM06474
Permit Status: Fees paid
Permit Description: TI: Existing Auto Dealership - Building 1
Date Description Comments
04/17/2024 AIR BALANCING REPORT IS REQUIRED.
09/17/2024 Provide verification of Pima County sewer connection review, IWC approval and payment of associated fees. Please contact Pima County DSD-Building Codes/Wastewater (520)-724-6503
04/17/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Fees Paid
Permit Number: T22CM06474
Permite Description: TI: Existing Auto Dealership - Building 1
Total Outstanding Inspections - 22
Last Inspection Date Description Inspector Results Comments
12/13/2023 COT - HCBU - Roof Nailing N/A Not Applicable
12/13/2023 COT - HCBU - Building Above Ceiling N/A Partial Pass 12/13/23: partial for sales offices, f and I offices, hallway, greeter, and BDC areas
09/29/2023 COT - HCBU - Excavation/Rebar/Zoning N/A Canceled 6/21/23: footings for new car delivery canopy approved to pour. Footings for north side mats at entrance approved to pour.
8/17/23: footing for entrance ramp on north side of building. Pour-back over electric conduit on showroom floor.
9/18/23: 4 reinforced pads and footing reinforcing at Service Drive approved.
9/29/23: inspection cancelled per A.J.
12/13/2023 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 12/13/23: partial for sales offices, f and I offices, hallway, greeter, and BDC areas
12/13/2023 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 12/13/23: partial for sales offices, f and I offices, hallway, greeter, and BDC areas
12/13/2023 COT - LCEL - Electrical Above Ceiling N/A Partial Pass 12/13/23: partial for sales offices, f and I offices, hallway, greeter, and BDC areas
07/22/2024 COT - HCEL - Electrical Final N/A Partial Pass Level Three for Showroom and Service Writer.
06/28/2024 COT - FCON - Sprinkler - Final N/A Partial Pass Sprinklers in north building east of car wash approved.
07/31/2024 COT - FCON - Fire - Final N/A Partial Pass Showroom and advisor area approved for level 4 TCO. South buildings need to be approved still. South riser needs to be tied into FA.
09/07/2023 COT - HCBU - Building Progress N/A Canceled
09/05/2024 COT - HCPL - Plumbing Progress N/A Partial Pass Exterior sewer from Women's tech to tie in.
09/17/2024 COT - HCPL - Plumbing Intermediate N/A Re-inspection required 9/17/24; protect pvc penetrating steel studs. Copper pipe needs to be secured to wall.
12/13/2023 COT - HCME - Mechanical Intermediate N/A Partial Pass 12/13/23: partial for sales offices, f and I offices, hallway, greeter, and BDC areas
07/23/2024 ENGR Engineering Final N/A Not Ready This will be recalled for next week as a TCO4 release for the left side of the service garage, parking on the east side of same to include the ADA parking and accessible lane into and around to the front of the building. Behind the garage they will fence off the exit from the garage to the actual service area. New ADA non accessible sign and yellow warning stripe will be painted prior to inspection and all construction materials will be removed.
12/26/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass 12/26/23 customer work service, advisors, service, advisors, managers, office, parts, and cashier area
10/06/2023 COT - HCBU - Masonry Pregrout N/A Partial Pass 9/26/23: stem reinforcing for new CMU walls at the New Service Drive Extension.
9/28/23: 1st lift at New Service Drive extension
9/29/23: 2nd lift at New Service Drive extension.
10/2/23: 3rd lift at New Service Drive extension.
10/6/23: top-out lift at New Service extension.
10/11/2023 COT - HCEL - Electrical Underground N/A Partial Pass Existing SES partial for lines to Panels S-M, primaries for new SES panel from panel to fire line valve.
10/24/2024 PDSD Building Division - Site Excavation/Layout/Rebar N/A Partial Pass 8" air gap in meeting room.
12/09/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass West building of showroom and meeting room.
12/13/2023 COT - HCBU - Framing N/A Partial Pass 12/13/23: partial for cashier parts display and advisors area framing okay to cover
12/18/2024 COT - HCBU - Preslab N/A Partial Pass 12-18-24, preslab for south service bay verified as per approved plans. Okay to pour 88 yards of concrete (partial pass).
12/09/2024 COT - LCBU - Masonry Pregrout N/A Partial Pass Top out at meeting room and stemwall for South service bays.

Completed Inspections

Permit Status: Fees Paid
Permit Number: T22CM06474
Permit Description: TI: Existing Auto Dealership - Building 1
Total Completed Inspections - 14
Date Description Inspector Results Comments
10/31/2023 COT - HCEL - Electrical Progress Passed
02/13/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
05/10/2024 BULD - Electrical Clearance Passed Approved 1200A SES cabinet "H" connected to transformer, ECO Clearance to TEP is required
07/22/2024 COT - HCME - Mechanical Final Passed
07/22/2024 COT - HCBU - Building Final Passed
07/22/2024 COT - HCBU - TCO Passed Level Three for Showroom and Service Writer.
07/22/2024 COT - HCPL - Plumbing Final Passed
08/30/2024 COT - HCBU - Building Progress Passed
10/16/2024 COT - HCEL - Outdoor Lighting Passed 10/16/24: parking lot lights north side of building complete.
11/04/2024 COT - HCBU - Interior Shear Bracing Passed Finals for service tech bathrooms.
11/20/2024 COT - HCBU - Masonry Pregrout Passed 11/20/24: okay to grout 2nd lift of wall between office area and service bay on south side.
12/03/2024 PDSD Building Division - Site Excavation/Layout/Rebar Passed Southwest service bays. East and west end connecting to existing footers approved. Okay for concrete placement. 12/3/2024
12/09/2024 COT - HCBU - Framing Passed
12/12/2024 COT - HCPL - Rough Soil Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
JIM CLICK HYUNDAI EASTSIDE - REPORT T-B_V1.PDF DOCUMENTS VIEW
JIM CLICK HYUNDAI-EASTSIDE (CHLORINATION REPORT)-2024-07-29_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
REV4_NARRATIVE_V1.PDF DOCUMENTS VIEW
REV4_PLAN SET_V1.PDF DOCUMENTS VIEW
REV4_STRUC CALCS_V1.PDF DOCUMENTS VIEW
REV3_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
REV3_PLAN SET_V1.PDF DOCUMENTS VIEW
REV2_2_PLAN SET_V1.PDF DOCUMENTS VIEW
REV2_COMMENT RESPONSE_V1.PDF DOCUMENTS VIEW
CONS-REV1_PLAN SET_V1.PDF DOCUMENTS VIEW
REV1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - ARCHITECTURAL_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - ELECTRICAL_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - MECHANICAL_V1.PDF DOCUMENTS VIEW
2_DELTA 2 REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
CONS-2_BUILDING PLANS_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - ARCHITECTURAL_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - ELECTRICAL_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER - MECHANICAL_V1.PDF DOCUMENTS VIEW
2_DELTA 2 REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
CONS-2_BUILDING PLANS_V1.PDF DOCUMENTS VIEW